United States βΊ Grid βΊ Interconnection queues βΊ Delaware
BATTERY STORAGE Β· PJMBattery storage project AH1-761, New Castle County
Battery storage project AH1-761, New Castle County is a 71.0 MW battery storage request withdrawn in the PJM interconnection queue, in New Castle County, Delaware, connecting to DPL.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-761
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Developer
- Freepoint Solar LLC
- Location
- New Castle County, Delaware
- Technology
- Battery: 71.0 MW
- Total requested
- 71.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Proposed online date
- April 2029
- Withdrawn
- May 2025
Location
Marker shows the centre of New Castle County; the queue data does not give exact sites.
Other requests in New Castle County
- Battery storage project AH2-051, New Castle CountyBattery storage Β· 200 MW Β· in study
- Solar project AG2-447, New Castle CountySolar Β· 20.0 MW Β· in study
- Other project AI2-025, New Castle CountyOther Β· 10.0 MW Β· in study
- Cedar Creek SolarSolar Β· 19.8 MW Β· suspended
- Cedar Creek SolarSolar Β· 19.8 MW Β· suspended
- Cedar Creek SolarSolar Β· 18.8 MW Β· suspended
- Cedar Creek SolarSolar Β· 15.9 MW Β· suspended
- Hay Road 5, 6, 7Gas Β· 545 MW Β· built
- Garrison Energy CenterGas Β· 309 MW Β· built
- Delaware CityOther Β· 250 MW Β· built
- Delaware City/Motiva Unit G6Gas Β· 60.0 MW Β· built
- New Castle SolarSolar Β· 50.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem