United States โ€บ Grid โ€บ Interconnection queues โ€บ California

OCTARY USA ยท INTERCONNECTION QUEUES

Battery storage interconnection queue in California

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown19753.6 GW
Active in queue53.6 GW197 requests
Agreement signed22.0 GW81 requests
Withdrawn590142.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

197 requests ยท page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Pion
Battery storage
1,168 MWIn study Fresno, CACAISO Apr 2023target 2028
Hillside Energy Storage
Battery storage
1,065 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Crusade
Battery storage
1,029 MWIn study Orange, CACAISO Apr 2023target 2028
Lagoonez
Battery storage
1,029 MWIn study Los Angeles, CACAISO Apr 2023target 2028
Battery storage project Q112, San Bernardino County
Battery storage
1,000 MWIn study San Bernardino, CAWest Oct 2024target 2028
Irving Storage
Battery storage
783 MWAgreement signed Monterey, CACAISO May 2019target 2025
Menifee Power Bank
Battery storage
680 MWAgreement signed Riverside, CACAISO Apr 2019target 2025
Steel City Battery Storage
Battery storage
675 MWAgreement signed Contra Costa, CACAISO Apr 2020target 2029
Yuha Desert Battery Storage
Battery storage
633 MWIn study Imperial, CACAISO Apr 2021target 2031
Sagebrush Energy Storage
Battery storage
528 MWIn study Kern, CACAISO Apr 2021target 2033
Summit Valley Energy Storage
Battery storage
519 MWIn study San Bernardino, CACAISO Apr 2023target 2032
Lupine Energy Center
Battery storage
518 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Chronos Energy Storage
Battery storage
517 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Alta Casa Storage
Battery storage
515 MWAgreement signed San Joaquin, CACAISO Apr 2021target 2031
Yacht Rock
Battery storage
514 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Dove Cove
Battery storage
514 MWIn study San Joaquin, CACAISO Apr 2023target 2031
Belterra Energy Storage
Battery storage
514 MWIn study Calaveras, CACAISO Apr 2023target 2028
Fontus
Battery storage
514 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Greasewood Energy Storage
Battery storage
513 MWAgreement signed Kern, CACAISO Apr 2021target 2033
Conduit Energy Storage
Battery storage
513 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Rosa Storage
Battery storage
512 MWIn study Ventura, CACAISO Apr 2021target 2034
Lock Storage
Battery storage
508 MWAgreement signed Fresno, CACAISO Apr 2021target 2027
Double Butte Storage
Battery storage
508 MWAgreement signed Riverside, CACAISO Apr 2019target 2030
Galicia Storage
Battery storage
506 MWIn study San Bernardino, CACAISO Apr 2023target 2028
Ambar Energy Storage
Battery storage
505 MWIn study San Bernardino, CACAISO Apr 2023target 2030
Drifter Energy Storage
Battery storage
505 MWAgreement signed Ventura, CACAISO Apr 2021target 2033
Spectrum Energy Storage
Battery storage
504 MWAgreement signed Alameda, CACAISO Apr 2021target 2032
Delilah Energy Storage
Battery storage
504 MWAgreement signed Contra Costa, CACAISO Apr 2021target 2032
Battery storage project Q108, San Bernardino County
Battery storage
500 MWIn study San Bernardino, CAWest Jun 2024target 2028
Lake Elsinore Advanced Pumped Storage Project
Battery storage
500 MWAgreement signed Riverside, CACAISO Jun 2005target 2028
Battery storage project Q78, Kern County
Battery storage
500 MWIn study Kern, CAWest Oct 2020target 2021
Goldback Solar Center
Battery storage
500 MWAgreement signed Ventura, CACAISO Apr 2019target 2026
Battery storage project Q84, San Bernardino County
Battery storage
500 MWIn study San Bernardino, CAWest Oct 2021target 2024
Corby 2
Battery storage
476 MWIn study Solano, CACAISO Apr 2021target 2031
Shoals Energy Storage 2
Battery storage
461 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Tolenas
Battery storage
417 MWIn study Solano, CACAISO Apr 2021target 2031
Dos Palmas
Battery storage
411 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Shoals Energy Storage
Battery storage
409 MWAgreement signed Ventura, CACAISO Apr 2020target 2030
Hidalgo Energy Storage
Battery storage
408 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2033
Simon
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Gabriel Storage
Battery storage
406 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2033
Trolley
Battery storage
406 MWAgreement signed San Bernardino, CACAISO Apr 2021target 2031
Coral Reef
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Fleetwood
Battery storage
406 MWIn study Los Angeles, CACAISO Apr 2021target 2032
Marici
Battery storage
406 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2031
Tea Leaf Energy Storage
Battery storage
404 MWIn study Alameda, CACAISO Apr 2023target 2030
Dirac
Battery storage
403 MWIn study San Bernardino, CACAISO Apr 2021target 2031
Brushy
Battery storage
400 MWIn study Solano, CACAISO Apr 2021target 2031
Battery storage project GI-2023-168, Imperial County
Battery storage
387 MWIn study Imperial, CAWest Apr 2023target 2025
Golden Flats
Battery storage
365 MWAgreement signed Stanislaus, CACAISO Apr 2021target 2031
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)