BATTERY STORAGE · WEST

Battery storage project Q84, San Bernardino County

Battery storage project Q84, San Bernardino County is a 500 MW battery storage request in interconnection study in the West interconnection queue, in San Bernardino County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Oct 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q84
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Adelanto 500kV Switchyard
Location
San Bernardino County, California
Technology
Battery: 500 MW
Total requested
500 MW
Study phase
Application received
Queue status
Active
Entered queue
18 October 2021
Proposed online date
May 2024

Location

Marker shows the centre of San Bernardino County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Bernardino County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem