πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Arkansas (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown256,903 MW
Active in queue6,903 MW25 requests
Agreement signed408 MW2 requests
Withdrawn262,805 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2261, Jackson County
Solar
625 MWIn study Jackson, ARMISO Oct 2021target 2028
Solar project J2262, Jackson County
Solar
625 MWIn study Jackson, ARMISO Oct 2021target 2028
Solar + storage project J1897, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Dec 2021target 2027
Solar + storage project J1899, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Dec 2021target 2027
Solar + storage project J2190, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Aug 2021target 2027
Solar project J1855, Jackson County
Solar
500 MWIn study Jackson, ARMISO Nov 2021target 2026
Solar project J1858, Mississippi County
Solar
440 MWIn study Mississippi, ARMISO Nov 2021target 2028
Solar project J2143, Chicot County
Solar
250 MWIn study Chicot, ARMISO Oct 2021target 2027
Solar project J1872, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Solar project J1873, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Solar project J2294, Mississippi County
Solar
250 MWIn study Mississippi, ARMISO Aug 2021target 2028
Solar project J2149, Saline County
Solar
240 MWIn study Saline, ARMISO Nov 2021target 2024
Solar project GEN-2021-033, Franklin County
Solar
204 MWAgreement signed Franklin, ARSPP May 2021target 2028
Solar project GEN-2021-036, Little River County
Solar
204 MWAgreement signed Little River, ARSPP May 2021target 2027
Solar project J2089, Mississippi County
Solar
200 MWIn study Mississippi, ARMISO Nov 2021target 2027
Solar + storage project J2153, Ashley County
Solar + storage
200 MWIn study Ashley, ARMISO Aug 2021target 2027
Solar project J2298, Greene County
Solar
200 MWIn study Greene, ARMISO Nov 2021target 2028
Solar project J2134, Grant County
Solar
200 MWIn study Grant, ARMISO Nov 2021target 2024
Solar project J2237, Lee County
Solar
185 MWIn study Lee, ARMISO Dec 2021target 2027
Solar project J1856, Jackson County
Solar
150 MWIn study Jackson, ARMISO Nov 2021target 2026
Onshore wind project J1842, Cross County
Onshore wind
135 MWIn study Cross, ARMISO Oct 2021target 2024
Solar + storage project J2133, White County
Solar + storage
100 MWIn study White, ARMISO Aug 2021target 2024
Solar project J1514, Mississippi County
Solar
100 MWUnder construction Mississippi, ARMISO Dec 20212024
Solar project J2010, Arkansas County
Solar
75.0 MWIn study Arkansas, ARMISO Aug 2021target 2028
Coal project J2081, Mississippi County
Coal
20.0 MWIn study Mississippi, ARMISO Aug 2021target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)