United States โ€บ Grid โ€บ Interconnection queues โ€บ Arkansas

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Arkansas

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32457.8 GW
Active in queue35.4 GW157 requests
Agreement signed1,783 MW13 requests
Withdrawn32457.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

324 requests ยท page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J433, Union County
Gas
1,270 MWWithdrawn / abandoned Union, ARMISO Jan 2015
Gas project GEN-2000-006, Sebastian County
Gas
660 MWWithdrawn / abandoned Sebastian, ARSPP
Gas project GEN-2000-012, Sebastian County
Gas
660 MWWithdrawn / abandoned Sebastian, ARSPP Nov 2000
Gas project J4111, Hot Spring County
Gas
650 MWWithdrawn / abandoned Hot Spring, ARMISO Oct 2025target 2030
Coal project GEN-2006-011, Hempstead County
Coal
605 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2006target 2011
Solar + storage project J2717, Hot Spring County
Solar + storage
600 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2029
Gas project GEN-2006-007, Washington County
Gas
530 MWWithdrawn / abandoned Washington, ARSPP Feb 2006target 2007
Solar project 597, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project J3530, Saline County
Solar
500 MWWithdrawn / abandoned Saline, ARMISO Apr 2024target 2028
Solar project J2785, Calhoun County
Solar
500 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2026
Solar project J2758, Jefferson County
Solar
500 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2025
Solar project J2399, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2025
Solar + storage project 592, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar + storage project 594, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar project J3626, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2027
Solar project J3426, Chicot County
Solar
500 MWWithdrawn / abandoned Chicot, ARMISO Mar 2024target 2028
Solar project J3386, Calhoun County
Solar
500 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2028
Solar project J2682, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project J2452, Cleveland County
Solar
500 MWWithdrawn / abandoned Cleveland, ARMISO Sep 2022target 2026
Other project J319, Pope County
Other
500 MWWithdrawn / abandoned Pope, ARMISO Dec 2013target 2018
Solar + storage project 593, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar project 599, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project J2936, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project 598, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project J3427, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2024target 2028
Solar project J3937, Dallas County
Solar
500 MWWithdrawn / abandoned Dallas, ARMISO Apr 2025target 2030
Solar project J1097, Lonoke County
Solar
500 MWWithdrawn / abandoned Lonoke, ARMISO Mar 2018target 2021
Battery storage project J3023, Hot Spring County
Battery storage
400 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2026
Solar project J3303, Prairie County
Solar
400 MWWithdrawn / abandoned Prairie, ARMISO Apr 2024target 2027
Solar project J3388, Calhoun County
Solar
400 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2028
Solar project J3540, Monroe County
Solar
400 MWWithdrawn / abandoned Monroe, ARMISO Apr 2024target 2028
Solar project GEN-2024-156, Howard County
Solar
400 MWWithdrawn / abandoned Howard, ARSPP Mar 2025target 2029
Solar project J3711, Calhoun County
Solar
400 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2029
Solar + storage project J3110, Craighead County
Solar + storage
400 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2026
Solar project J2640, Calhoun County
Solar
395 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2025
Solar project J2510, Jefferson County
Solar
350 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar project J3304, Clark County
Solar
350 MWWithdrawn / abandoned Clark, ARMISO Apr 2024target 2027
Solar project GEN-2022-239, Hempstead County
Solar
350 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2023target 2028
Gas project GEN-2000-010, Pulaski County
Gas
340 MWWithdrawn / abandoned Pulaski, ARSPP
Solar project J3570, Cross County
Solar
300 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Solar project J2516, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar project J3048, Crawford County
Solar
300 MWWithdrawn / abandoned Crawford, ARMISO Sep 2022target 2027
Solar project J3575, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Solar + storage project J3583, Lonoke County
Solar + storage
300 MWWithdrawn / abandoned Lonoke, ARMISO Apr 2024target 2028
Solar project J3802, Phillips County
Solar
300 MWWithdrawn / abandoned Phillips, ARMISO Apr 2024target 2028
Solar project J3569, Poinsett County
Solar
300 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Solar project J2090, Crittenden County
Solar
300 MWWithdrawn / abandoned Crittenden, ARMISO Jul 2022target 2026
Solar + storage project J3747, Lonoke County
Solar + storage
300 MWWithdrawn / abandoned Lonoke, ARMISO Apr 2024target 2028
Solar project J3171, Drew County
Solar
300 MWWithdrawn / abandoned Drew, ARMISO Sep 2022target 2026
Solar project J1078, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)