United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Alabama (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown295,137 MW
Active in queue5,137 MW29 requests
Agreement signed0.0 MW0 requests
Withdrawn121,645 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

29 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 25-IC-1382, Mobile County
Gas
707 MWIn study Mobile, ALSoutheast Apr 2025target 2031
Gas project 25RSC-011, Morgan County
Gas
528 MWIn study Morgan, ALSoutheast Aug 2025target 2031
Battery storage project 25RSC-008, Jackson County
Battery storage
300 MWIn study Jackson, ALSoutheast Jul 2025target 2030
Solar + storage project 25-IC-1315, Mobile County
Solar + storage
295 MWIn study Mobile, ALSoutheast Apr 2025target 2029
Gas project 25-IC-1320A, Lee County
Gas
240 MWIn study Lee, ALSoutheast Apr 2025target 2029
Gas project 25-IC-1317, Autauga County
Gas
229 MWIn study Autauga, ALSoutheast Apr 2025target 2029
Solar + storage project 25-IC-1379, Butler County
Solar + storage
200 MWIn study Butler, ALSoutheast Apr 2025target 2028
Solar project 25-IC-1368, Mobile County
Solar
200 MWIn study Mobile, ALSoutheast Apr 2025target 2029
Solar + storage project 25-IC-1380, Escambia County
Solar + storage
200 MWIn study Escambia, ALSoutheast Apr 2025target 2028
Solar project 25-IC-1376, Baldwin County
Solar
199 MWIn study Baldwin, ALSoutheast Apr 2025target 2028
Battery storage project 25-IC-1358, Montgomery County
Battery storage
199 MWIn study Montgomery, ALSoutheast Apr 2025target 2029
Solar + storage project 25-IC-1356, Greene County
Solar + storage
199 MWIn study Greene, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1347, Escambia County
Solar
199 MWIn study Escambia, ALSoutheast Apr 2025target 2028
Solar project 25-IC-1365, Greene County
Solar
195 MWIn study Greene, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1361, Cherokee County
Solar
170 MWIn study Cherokee, ALSoutheast Apr 2025target 2029
Solar + storage project 25-IC-1370, Perry County
Solar + storage
160 MWIn study Perry, ALSoutheast Apr 2025target 2028
Gas project 25-IC-1321, Lee County
Gas
111 MWIn study Lee, ALSoutheast Apr 2025target 2029
Gas project 25-IC-1318, Autauga County
Gas
111 MWIn study Autauga, ALSoutheast Apr 2025target 2031
Gas project 25-IC-1319, Autauga County
Gas
111 MWIn study Autauga, ALSoutheast Apr 2025target 2032
Solar project 25-IC-1366, Dale County
Solar
110 MWIn study Dale, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1336, Clarke County
Solar
93.0 MWIn study Clarke, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1354, Dale County
Solar
91.0 MWIn study Dale, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1360, Sumter County
Solar
75.0 MWIn study Sumter, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1357, Monroe County
Solar
71.0 MWIn study Monroe, ALSoutheast Apr 2025target 2029
Nuclear project 25-IC-1307, Houston County
Nuclear
50.0 MWIn study Houston, ALSoutheast Apr 2025target 2031
Nuclear project 25-IC-1309, Houston County
Nuclear
50.0 MWIn study Houston, ALSoutheast Apr 2025target 2031
Nuclear project 25-IC-1308, Houston County
Nuclear
15.0 MWIn study Houston, ALSoutheast Apr 2025target 2029
Nuclear project 25-IC-1306, Houston County
Nuclear
15.0 MWIn study Houston, ALSoutheast Apr 2025target 2030
Gas project 25-IC-1344, Mobile County
Gas
14.0 MWIn study Mobile, ALSoutheast Apr 2025target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)