United States βΊ Grid βΊ Interconnection queues βΊ Alabama
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Alabama (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project IC-968, Lowndes County Solar |
300 MW | Withdrawn / abandoned |
| Solar project 480, Colbert County Solar |
170 MW | Withdrawn / abandoned |
| Solar project IC-984, Mobile County Solar |
160 MW | Withdrawn / abandoned |
| Solar project IC-983, Mobile County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-998, Baldwin County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-939, Covington County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-940, Covington County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar project IC-1004, Marengo County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-985, Marengo County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-970, Cherokee County Solar + storage |
80.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-929, Escambia County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-931, Dale County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar project IC-969, Bullock County Solar |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-930, Macon County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-928, Dale County Solar + storage |
79.0 MW | Withdrawn / abandoned |
| Solar + storage project IC-953, Perry County Solar + storage |
75.0 MW | Withdrawn / abandoned |
| Battery storage project 479, Jackson County Battery storage |
71.0 MW | Withdrawn / abandoned |
| Solar project IC-982, Mobile County Solar |
68.0 MW | Withdrawn / abandoned |
| Solar project 490, Lawrence County Solar |
68.0 MW | Withdrawn / abandoned |
| Solar project IC-967, Lowndes County Solar |
30.0 MW | Withdrawn / abandoned |
| Battery storage project 467, Lawrence County Battery storage |
17.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)