πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7221.7 GW
Active in queue21.7 GW72 requests
Agreement signed3,861 MW26 requests
Withdrawn24741.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

72 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q68, Los Angeles County
Solar + storage
2,400 MWIn study Los Angeles, CAWest Mar 2019target 2022
Onshore wind project Q320, San Juan County
Onshore wind
1,500 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Solar + storage project G0615, Sherman County
Solar + storage
1,200 MWIn study Sherman, ORWest Feb 2019target 2021
Onshore wind project Q318, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Onshore wind project Q319, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Other project Company KD, White Pine County
Other
750 MWPaused / redesign White Pine, NVWest Sep 2019target 2026
Solar + storage project Q317, Coconino County
Solar + storage
750 MWIn study Coconino, AZWest Sep 2019target 2023
Onshore wind project 366, Rosebud County
Onshore wind
600 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Onshore wind project C006, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Feb 2019target 2021
Onshore wind project 82, Meagher County
Onshore wind
600 MWAgreement signed Meagher, MTWest Feb 2019
Onshore wind project 361, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Mar 2019target 2021
Wind + storage project Q311, Navajo County
Wind + storage
500 MWIn study Navajo, AZWest Sep 2019target 2021
Solar + storage project Q28, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Oct 2019target 2027
Onshore wind project G0619, Wasco County
Onshore wind
500 MWIn study Wasco, ORWest Apr 2019target 2023
Solar + storage project Q67, Clark County
Solar + storage
500 MWIn study Clark, NVWest Mar 2019target 2022
Solar + storage project IA-PNM-2019-11, San Juan County
Solar + storage Β· 450CT 8ME
500 MWAgreement signed San Juan, NMWest Apr 2019target 2025
Solar project Q312, Coconino County
Solar
500 MWIn study Coconino, AZWest Sep 2019target 2021
Solar + storage project Q310, Yuma County
Solar + storage
450 MWAgreement signed Yuma, AZWest Aug 2019target 2023
Onshore wind project 367, Rosebud County
Onshore wind
400 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Solar + storage project Company JX, Pershing County
Solar + storage
340 MWPaused / redesign Pershing, NVWest Sep 2019target 2023
Onshore wind project 83, Meagher County
Onshore wind
300 MWAgreement signed Meagher, MTWest Mar 2019
Onshore wind project 71, Meagher County
Onshore wind
300 MWPaused / redesign Meagher, MTWest Mar 2019target 2029
Onshore wind project C007, Meagher County
Onshore wind
300 MWIn study Meagher, MTWest Mar 2019target 2022
Onshore wind project 362, Wheatland County
Onshore wind
300 MWPaused / redesign Wheatland, MTWest Apr 2019target 2022
Solar + storage project 573, Power County
Solar + storage Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Power, IDWest Nov 2019target 2027
Battery storage project Q314, Maricopa County
Battery storage
300 MWIn study Maricopa, AZWest Sep 2019target 2022
Solar + storage project 2019-G1, Butte County
Solar + storage
300 MWIn study Butte, CAWest Aug 2019target 2027
Solar + storage project G0617, Sherman County
Solar + storage
300 MWIn study Sherman, ORWest Mar 2019target 2022
Solar + storage project Q295, Pinal County
Solar + storage
250 MWAgreement signed Pinal, AZWest Mar 2019target 2022
Solar project GI-2019-6, Pueblo County
Solar
240 MWIn study Pueblo, COWest May 20192021
Solar + storage project 551, Elmore County
Solar + storage Β· Bennett Solar B LLC
240 MWPaused / redesign Elmore, IDWest Apr 2019target 2026
Onshore wind project 360, Wheatland County
Onshore wind
200 MWPaused / redesign Wheatland, MTWest Feb 2019target 2021
Solar + storage project Company 181, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2019target 2028
Solar + storage project 99, Franklin County
Solar + storage
200 MWIn study Franklin, WAWest Sep 2019target 2021
Solar project G0625, Morrow County
Solar
191 MWIn study Morrow, ORWest Jun 2019target 2020
Solar + storage project 2019-G42, San Bernardino County
Solar + storage
160 MWIn study San Bernardino, CAWest Jun 2019target 2021
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Battery storage project IA-PNM-2019-19, Bernalillo County
Battery storage Β· PNM β€šΓ„Γ¬ Generation
150 MWAgreement signed Bernalillo, NMWest Apr 2019target 2021
LA130S Project
Solar + storage
130 MWIn study Luna, NMWest Mar 2019target 2026
Solar + storage project IA-PNM-2019-08, Mckinley County
Solar + storage Β· RWE Solar Dev
125 MWPaused / redesign Mckinley, NMWest Apr 2019target 2022
Solar project 558, Jerome County
Solar Β· Cat Creek Energy, LLC
120 MWAgreement signed Jerome, IDWest May 2019target 2026
CO100SB Project
Solar + storage
100 MWAgreement signed Otero, NMWest Mar 2019target 2027
Solar + storage project 100, Benewah County
Solar + storage
100 MWIn study Benewah, IDWest Sep 2019target 2021
Battery storage project IA-PNM-2019-18, Bernalillo County
Battery storage
100 MWPaused / redesign Bernalillo, NMWest Apr 2019target 2022
Solar + storage project Company 174, Clark County
Solar + storage
100 MWAgreement signed Clark, NVWest Mar 2019target 2023
VE100S Project
Solar + storage
100 MWAgreement signed Dona Ana, NMWest Sep 2019target 2026
Solar + storage project 97, Nez Perce County
Solar + storage
100 MWPaused / redesign Nez Perce, IDWest Jun 2019target 2025
Battery storage project Company JW, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2019target 2027
Solar + storage project IA-PNM-2019-05, Santa Fe County
Solar + storage
96.0 MWAgreement signed Santa Fe, NMWest Apr 2019target 2021
Solar + storage project Q313, Yavapai County
Solar + storage
95.0 MWIn study Yavapai, AZWest Sep 2019target 2022
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)