United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) (2023 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Nuclear project G0869, Benton County Nuclear |
2,200 MW | Withdrawn / abandoned |
| Solar + storage project Q109, Navajo County Solar + storage |
2,000 MW | Withdrawn / abandoned |
| Solar + storage project Q33, Pinal County Solar + storage |
2,000 MW | Withdrawn / abandoned |
| Solar + storage project Company PM, Esmeralda County Solar + storage |
1,500 MW | Withdrawn / abandoned |
| Solar + storage project G0852, Wasco County Solar + storage |
1,500 MW | Withdrawn / abandoned |
| Hydro project Q499, Riverside County Hydro |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0966, Umatilla County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0962, Morrow County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0960, Morrow County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0964, Umatilla County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0983, Sherman County Solar + storage |
1,200 MW | Withdrawn / abandoned |
| Solar + storage project G1019, Klamath County Solar + storage |
1,024 MW | Withdrawn / abandoned |
| Solar + storage project G1024, Lake County Solar + storage |
1,024 MW | Withdrawn / abandoned |
| Solar + storage project G1018, Klamath County Solar + storage |
1,024 MW | Withdrawn / abandoned |
| Solar + storage project G1020, Klamath County Solar + storage |
1,024 MW | Withdrawn / abandoned |
| Solar + storage project G1023, Lake County Solar + storage |
1,024 MW | Withdrawn / abandoned |
| Solar + storage project G0874, Sherman County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project Company OZ, Esmeralda County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Other project 156, Pima County Other |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project Company PB, Esmeralda County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project G0931, Sherman County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project Q508, Maricopa County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Onshore wind project G0848, Coos County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Other project 157, Pima County Other |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project G0846, Klickitat County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project Company 240, Nye County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project G0875, Lake County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Solar project C3-052, Carbon County Solar |
1,000 MW | Withdrawn / abandoned |
| Solar + storage project 23-230, Jefferson County Solar + storage |
1,000 MW | Withdrawn / abandoned |
| Wind + storage project Company QI, Esmeralda County Wind + storage |
960 MW | Withdrawn / abandoned |
| Solar + storage project Q102, Mohave County Solar + storage |
930 MW | Withdrawn / abandoned |
| Battery storage project C3-013, Carbon County Battery storage |
900 MW | Withdrawn / abandoned |
| Other project 155, Cochise County Other |
800 MW | Withdrawn / abandoned |
| Solar + storage project Q14, Maricopa County Solar + storage |
800 MW | Withdrawn / abandoned |
| Solar + storage project G0851, Sherman County Solar + storage |
800 MW | Withdrawn / abandoned |
| Other project Q99, White Pine County Other Β· Intermountain Power Agency |
800 MW | Withdrawn / abandoned |
| Solar + storage project G0926, Benton County Solar + storage |
750 MW | Withdrawn / abandoned |
| Solar + storage project G0928, Benton County Solar + storage |
750 MW | Withdrawn / abandoned |
| Solar + storage project GI-2023-17, Crowley County Solar + storage |
750 MW | Withdrawn / abandoned |
| Solar + storage project G0927, Benton County Solar + storage |
750 MW | Withdrawn / abandoned |
| Other project Q512, Mohave County Other |
700 MW | Withdrawn / abandoned |
| Solar + storage project G1000, Morrow County Solar + storage |
660 MW | Withdrawn / abandoned |
| Solar + storage project Q506, Maricopa County Solar + storage |
660 MW | Withdrawn / abandoned |
| Battery storage project G0952, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0951, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0959, Umatilla County Battery storage |
650 MW | Withdrawn / abandoned |
| Solar + storage project G0930, Benton County Solar + storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0950, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0949, Gilliam County Battery storage |
650 MW | Withdrawn / abandoned |
| Battery storage project G0961, Umatilla County Battery storage |
650 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)486 Β· 198.6 GW
- West (non-ISO utilities)547 Β· 166.5 GW
- SPP (Southwest Power Pool)336 Β· 71.5 GW
- NYISO (New York)138 Β· 40.7 GW
- Southeast (non-ISO utilities)331 Β· 40.7 GW
- ERCOT (Texas)85 Β· 16.1 GW
- ISO-NE (New England)119 Β· 15.7 GW
- MISO (Midcontinent)10 Β· 1,143 MW
- PJM (Mid-Atlantic, Midwest)11 Β· 867 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)