United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) (2015 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project 711, Klamath County Battery storage |
416 MW | Withdrawn / abandoned |
| Solar + storage project 718, Lake County Solar + storage |
400 MW | Withdrawn / abandoned |
| Gas project Company HA, Washoe County Gas |
360 MW | Withdrawn / abandoned |
| Onshore wind project GI-2015-1, Elbert County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project 207, Yellowstone County Solar |
250 MW | Withdrawn / abandoned |
| Solar project 2015-G1 Solar |
250 MW | Withdrawn / abandoned |
| Gas project 43, Pima County Gas |
206 MW | Withdrawn / abandoned |
| Solar project 710, Kane County Solar |
204 MW | Withdrawn / abandoned |
| CA200S PV Project Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project 644, Navajo County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G0515, Lewis County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project 42, Lewis County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project 46, Adams County Onshore wind |
126 MW | Withdrawn / abandoned |
| Gas project CLPT G6, Laramie County Gas Β· Cheyenne Light, Fuel & Power |
125 MW | Withdrawn / abandoned |
| Solar project 705, Morrow County Solar |
100 MW | Withdrawn / abandoned |
| Solar project Company 146, Clark County Solar |
100 MW | Withdrawn / abandoned |
| Solar project Company GY, Lyon County Solar |
100 MW | Withdrawn / abandoned |
| Solar project Company 143, Clark County Solar |
100 MW | Withdrawn / abandoned |
| Solar project Company GZ, Lyon County Solar |
100 MW | Withdrawn / abandoned |
| Solar project 683, Beaver County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 45, Kittitas County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project Company 145, Clark County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project Company GL, Pershing County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project Company GO, Lyon County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project BHCT G20, Pueblo County Solar Β· Black Hills Electric Generation LLC |
60.0 MW | Withdrawn / abandoned |
| Other project 658, Clark County Other Β· OR Solar 4, LLC |
60.0 MW | Withdrawn / abandoned |
| Solar project Company GN, Pershing County Solar |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project 714, Washington County Onshore wind |
52.9 MW | Withdrawn / abandoned |
| Onshore wind project 717, Washington County Onshore wind |
51.0 MW | Withdrawn / abandoned |
| Solar project Company GE, Nye County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q36, Pinal County Solar |
48.0 MW | Withdrawn / abandoned |
| Solar project BHCT G17, Pueblo County Solar |
46.4 MW | Withdrawn / abandoned |
| Solar project G0510, Deschutes County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project 2015-G1, Merced County Solar |
26.0 MW | Withdrawn / abandoned |
| Onshore wind project 210, Judith Basin County Onshore wind |
25.0 MW | Withdrawn / abandoned |
| Onshore wind project 209, Sweet Grass County Onshore wind |
25.0 MW | Withdrawn / abandoned |
| Solar project 664, Bonneville County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 484, Minidoka County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Company GS, Douglas County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 668, Jefferson County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Company GM, Churchill County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 483, Ada County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 685, Beaver County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 459, Camas County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 206, Davison County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar project G0512, Umatilla County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 647, Iron County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 467, Elmore County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 482, Ada County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 463, Bingham County Solar |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)231 Β· 27.2 GW
- MISO (Midcontinent)53 Β· 17.2 GW
- CAISO (California)91 Β· 12.3 GW
- SPP (Southwest Power Pool)72 Β· 11.1 GW
- ISO-NE (New England)46 Β· 7,500 MW
- West (non-ISO utilities)197 Β· 6,025 MW
- ERCOT (Texas)28 Β· 5,278 MW
- Southeast (non-ISO utilities)49 Β· 4,719 MW
- NYISO (New York)33 Β· 4,251 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)