Solar project 685, Beaver County

Solar project 685, Beaver County is a 20.0 MW solar request withdrawn in the West interconnection queue, in Beaver County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
685
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
New 138kV Beaver to Milford line (in construction)
Location
Beaver County, Utah
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
13 July 2015
Proposed online date
December 2015

Location

Marker shows the centre of Beaver County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Beaver County