Withdrawn queue requests in Idaho, West

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown55685.2 GW
Active in queue21.0 GW83 requests
Agreement signed4,070 MW23 requests
Withdrawn55685.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

556 requests Β· page 1 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project C2-19, Kootenai County
Battery storage Β· PacifiCorp
1,800 MWWithdrawn / abandoned Kootenai, IDWest Apr 2022target 2028
Other project 63, Power County
Other
1,577 MWWithdrawn / abandoned Power, IDWest Sep 2001target 2004
Wind + storage project 570, Jerome County
Wind + storage Β· Magic Valley Energy, LLC
1,050 MWWithdrawn / abandoned Jerome, IDWest Oct 2019target 2023
Wind + storage project 587, Jerome County
Wind + storage Β· Magic Valley Energy, LLC
1,050 MWWithdrawn / abandoned Jerome, IDWest Aug 2020target 2023
Onshore wind project 563, Bonneville County
Onshore wind
950 MWWithdrawn / abandoned Bonneville, IDWest Aug 2019
Other project 530, Elmore County
Other Β· Cat Creek Energy, LLC
870 MWWithdrawn / abandoned Elmore, IDWest Apr 2018target 2020
Coal project 19, Elmore County
Coal
800 MWWithdrawn / abandoned Elmore, IDWest Apr 2003target 2009
Other project 65, Power County
Other
778 MWWithdrawn / abandoned Power, IDWest Sep 2001target 2004
Other project 66, Power County
Other
778 MWWithdrawn / abandoned Power, IDWest Sep 2001target 2004
Coal project 106, Elmore County
Coal
750 MWWithdrawn / abandoned Elmore, IDWest Apr 2004target 2011
Other project 524, Elmore County
Other
750 MWWithdrawn / abandoned Elmore, IDWest Aug 2017
Coal project 109, Elmore County
Coal
750 MWWithdrawn / abandoned Elmore, IDWest Jun 2004target 2011
Coal project 146, Jerome County
Coal
725 MWWithdrawn / abandoned Jerome, IDWest Jul 2005target 2011
Gas project 213, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Dec 2007target 2012
Gas project 242, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Apr 2008target 2012
Gas project 217, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Dec 2007target 2012
Gas project 261, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Jun 2008target 2012
Gas project 246, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Apr 2008target 2012
Gas project 211, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Dec 2007target 2012
Gas project 254, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest May 2008target 2012
Gas project 238, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Apr 2008target 2012
Gas project 214, Canyon County
Gas
650 MWWithdrawn / abandoned Canyon, IDWest Dec 2007target 2012
Gas project 210, Canyon County
Gas
650 MWWithdrawn / abandoned Canyon, IDWest Dec 2007target 2012
Gas project 240, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Apr 2008target 2012
Gas project 230, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Dec 2007target 2012
Gas project 219, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Dec 2007target 2012
Battery storage project 1168, Bannock County
Battery storage
650 MWWithdrawn / abandoned Bannock, IDWest Sep 2019target 2021
Gas project 249, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Apr 2008target 2012
Gas project 216, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Dec 2007target 2012
Gas project 212, Ada County
Gas
650 MWWithdrawn / abandoned Ada, IDWest Dec 2007target 2012
Gas project 218, Elmore County
Gas
650 MWWithdrawn / abandoned Elmore, IDWest Dec 2007target 2012
Gas project 247, Payette County
Gas
650 MWWithdrawn / abandoned Payette, IDWest Apr 2008target 2012
Gas project 243, Gem County
Gas
650 MWWithdrawn / abandoned Gem, IDWest Apr 2008target 2012
Other project 53, Payette County
Other
600 MWWithdrawn / abandoned Payette, IDWest Aug 2001target 2004
Hydro project G0502, Elmore County
Hydro
600 MWWithdrawn / abandoned Elmore, IDWest Nov 2014target 2017
Nuclear project 1065, Butte County
Nuclear
600 MWWithdrawn / abandoned Butte, IDWest Sep 2018target 2026
Onshore wind project 81, Butte County
Onshore wind
540 MWWithdrawn / abandoned Butte, IDWest May 2006target 2009
Battery storage project C4-019, Owyhee County
Battery storage
540 MWWithdrawn / abandoned Owyhee, IDWest May 2024target 2027
Wind + storage project 726, Owyhee County
Wind + storage
529 MWWithdrawn / abandoned Owyhee, IDWest Jun 2023target 2027
500MW Taft-Bell
Gas Β· Cogentrix Energy, Inc.
500 MWWithdrawn / abandoned Kootenai, IDWest Dec 2000target 2004
Other project 707, Elmore County
Other
500 MWWithdrawn / abandoned Elmore, IDWest Mar 2023
Solar + storage project 674, Ada County
Solar + storage
500 MWWithdrawn / abandoned Ada, IDWest Oct 2022
Solar + storage project 694, Canyon County
Solar + storage
500 MWWithdrawn / abandoned Canyon, IDWest Dec 2022
Solar + storage project 671, Lincoln County
Solar + storage
500 MWWithdrawn / abandoned Lincoln, IDWest Oct 2022
Solar project 560, Elmore County
Solar
500 MWWithdrawn / abandoned Elmore, IDWest Jun 2019
Solar + storage project C4-028, Blaine County
Solar + storage
500 MWWithdrawn / abandoned Blaine, IDWest May 2024target 2028
Other project 766, Elmore County
Other
495 MWWithdrawn / abandoned Elmore, IDWest Apr 2025
Solar + storage project 765, Ada County
Solar + storage
485 MWWithdrawn / abandoned Ada, IDWest Apr 2025
Nuclear project TCS-11, Butte County
Nuclear
462 MWWithdrawn / abandoned Butte, IDWest Sep 2018target 2029
Onshore wind project TCS-47, Bingham County
Onshore wind
450 MWWithdrawn / abandoned Bingham, IDWest Oct 2019target 2023
Page 1 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)