πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

WIND + STORAGE Β· WEST

Wind + storage project 570, Jerome County

Wind + storage project 570, Jerome County is a 1,050 MW wind + storage request withdrawn in the West interconnection queue, in Jerome County, Idaho, connecting to Idaho Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedMar 2022 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
570
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Magic Valley Energy, LLC
Connection point (POI)
MPSN 500kV
Location
Jerome County, Idaho
Technology
Wind: 1,050 MW Β· Battery
Total requested
1,050 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Withdrawn
Entered queue
17 October 2019
Agreement signed
23 March 2022
Proposed online date
December 2023

Location

Marker shows the centre of Jerome County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Jerome County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem