πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Battery storage interconnection queue in SPP (Southwest Power Pool)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown19831.4 GW
Active in queue31.4 GW198 requests
Agreement signed5,566 MW45 requests
Withdrawn21029.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

198 requests Β· page 1 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2020-057, Finney County
Battery storage
425 MWAgreement signed Finney, KSSPP Apr 2020target 2030
Battery storage project GEN-2025-SR1, Henry County
Battery storage
400 MWIn study Henry, MOSPP Apr 2025target 2027
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Battery storage project GEN-2024-230, Wilbarger County
Battery storage
300 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Battery storage project GEN-2024-331, Dunn County
Battery storage
300 MWIn study Dunn, NDSPP Mar 2025target 2028
Battery storage project GEN-2022-073, Clay County
Battery storage
300 MWIn study Clay, MOSPP Sep 2022target 2030
Battery storage project GEN-2021-006, Labette County
Battery storage
300 MWIn study Labette, KSSPP May 2021target 2026
Battery storage project GEN-2024-170, Cass County
Battery storage
280 MWIn study Cass, MOSPP Mar 2025target 2028
Battery storage project GEN-2025-SR28, Beaver County
Battery storage
263 MWIn study Beaver, OKSPP Aug 2025target 2027
Battery storage project GEN-2021-029, Linn County
Battery storage
254 MWIn study Linn, KSSPP May 2021target 2026
Battery storage project GEN-2024-171, Tulsa County
Battery storage
250 MWIn study Tulsa, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-242, Carter County
Battery storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Battery storage project GEN-2021-043, Lancaster County
Battery storage
250 MWAgreement signed Lancaster, NESPP Apr 2021target 2030
Battery storage project GEN-2024-367, Comanche County
Battery storage
250 MWIn study Comanche, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-368, Gray County
Battery storage
250 MWIn study Gray, TXSPP Mar 2025target 2028
Battery storage project ERAS-2025-027, Yoakum County
Battery storage
250 MWIn study Yoakum, TXSPP Oct 2025target 2028
Battery storage project GEN-2024-369, Grady County
Battery storage
250 MWIn study Grady, OKSPP Mar 2025target 2028
Battery storage project GEN-2024-217, Jackson County
Battery storage
250 MWIn study Jackson, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-371, Lea County
Battery storage
250 MWIn study Lea, NMSPP Mar 2025target 2028
Battery storage project GEN-2024-328, Slope County
Battery storage
250 MWIn study Slope, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-372, Douglas County
Battery storage
250 MWIn study Douglas, NESPP Mar 2025target 2028
Battery storage project GEN-2024-370, Clay County
Battery storage
250 MWIn study Clay, MOSPP Mar 2025target 2028
Battery storage project GEN-2024-176, Reno County
Battery storage
250 MWIn study Reno, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-062, Kingfisher County
Battery storage
230 MWIn study Kingfisher, OKSPP Oct 2024target 2028
Battery storage project GEN-2024-326, Stark County
Battery storage
225 MWIn study Stark, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-330, Butler County
Battery storage
225 MWIn study Butler, KSSPP Mar 2025target 2028
Battery storage project GEN-2025-SR8, Noble County
Battery storage
220 MWIn study Noble, OKSPP May 2025target 2027
Battery storage project GEN-2025-SR30, Dewey County
Battery storage
209 MWIn study Dewey, OKSPP Aug 2025target 2027
Battery storage project GEN-2019-011, Yoakum County
Battery storage
207 MWAgreement signed Yoakum, TXSPP Apr 2019target 2028
Battery storage project GEN-2020-090, Bourbon County
Battery storage
204 MWIn study Bourbon, KSSPP Apr 2020target 2026
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Battery storage project GEN-2020-081, Rusk County
Battery storage
200 MWAgreement signed Rusk, TXSPP Apr 2020target 2028
Battery storage project GEN-2023-037, Wyandotte County
Battery storage
200 MWIn study Wyandotte, KSSPP Oct 2023target 2028
Battery storage project GEN-2022-155, Oklahoma County
Battery storage
200 MWIn study Oklahoma, OKSPP Feb 2023target 2027
Battery storage project GEN-2024-SR11, Garfield County
Battery storage
200 MWAgreement signed Garfield, OKSPP May 20242025
Battery storage project GEN-2025-SR6, Grady County
Battery storage
200 MWIn study Grady, OKSPP Jun 2025target 2026
Battery storage project GEN-2022-142, Clay County
Battery storage
200 MWIn study Clay, MOSPP Feb 2023target 2030
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Battery storage project GEN-2022-144, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Feb 2023target 2030
Battery storage project GEN-2024-173, Lancaster County
Battery storage
200 MWIn study Lancaster, NESPP Mar 2025target 2028
Battery storage project GEN-2024-239, Canadian County
Battery storage
200 MWIn study Canadian, OKSPP Mar 2025target 2029
Battery storage project GEN-2022-130, Sebastian County
Battery storage
200 MWIn study Sebastian, ARSPP Feb 2023target 2030
Battery storage project GEN-2023-SR8, Hansford County
Battery storage
200 MWAgreement signed Hansford, TXSPP Feb 2023target 2026
Battery storage project GEN-2024-061, Cowley County
Battery storage
200 MWIn study Cowley, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-227, Hempstead County
Battery storage
200 MWIn study Hempstead, ARSPP Mar 2025target 2030
Battery storage project GEN-2019-012, Woodward County
Battery storage
200 MWAgreement signed Woodward, OKSPP May 2019target 2027
Page 1 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)