Gas project GEN-2024-207, Jackson County Gas |
779 MW | In study |
Jackson, MO | SPP |
Mar 2025 | target 2029 |
Gas project ERAS-2025-007, Nodaway County Gas |
451 MW | In study |
Nodaway, MO | SPP |
Oct 2025 | target 2030 |
Gas project ERAS-2025-013, Nodaway County Gas |
451 MW | In study |
Nodaway, MO | SPP |
Sep 2025 | target 2030 |
Battery storage project GEN-2025-SR1, Henry County Battery storage |
400 MW | In study |
Henry, MO | SPP |
Apr 2025 | target 2027 |
Solar project GEN-2017-108, Henry County Solar |
400 MW | Agreement signed |
Henry, MO | SPP |
Aug 2017 | target 2027 |
Solar project GEN-2024-289, Henry County Solar |
350 MW | In study |
Henry, MO | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2022-073, Clay County Battery storage |
300 MW | In study |
Clay, MO | SPP |
Sep 2022 | target 2030 |
Battery storage project GEN-2024-170, Cass County Battery storage |
280 MW | In study |
Cass, MO | SPP |
Mar 2025 | target 2028 |
Gas project ERAS-2025-034, Jasper County Gas |
250 MW | In study |
Jasper, MO | SPP |
Sep 2025 | target 2030 |
Battery storage project GEN-2024-217, Jackson County Battery storage |
250 MW | In study |
Jackson, MO | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2024-370, Clay County Battery storage |
250 MW | In study |
Clay, MO | SPP |
Mar 2025 | target 2028 |
Gas project GEN-2024-206, Jackson County Gas |
226 MW | In study |
Jackson, MO | SPP |
Mar 2025 | target 2026 |
Battery storage project GEN-2022-142, Clay County Battery storage |
200 MW | In study |
Clay, MO | SPP |
Feb 2023 | target 2030 |
Battery storage project GEN-2022-144, Jackson County Battery storage |
200 MW | In study |
Jackson, MO | SPP |
Feb 2023 | target 2030 |
Solar project GEN-2019-016, Polk County Solar |
200 MW | Agreement signed |
Polk, MO | SPP |
Apr 2019 | target 2029 |
Battery storage project GEN-2024-074, Jackson County Battery storage |
200 MW | In study |
Jackson, MO | SPP |
Oct 2024 | target 2028 |
Battery storage project GEN-2023-033, Clay County Battery storage |
200 MW | In study |
Clay, MO | SPP |
Oct 2023 | target 2028 |
Battery storage project GEN-2024-175, Greene County Battery storage |
200 MW | In study |
Greene, MO | SPP |
Mar 2025 | target 2028 |
Solar + storage project GEN-2024-259, Barton County Solar + storage |
200 MW | In study |
Barton, MO | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2024-260, Buchanan County Battery storage |
200 MW | In study |
Buchanan, MO | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2024-352, Jackson County Battery storage |
199 MW | In study |
Jackson, MO | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2024-167, Ray County Battery storage |
199 MW | In study |
Ray, MO | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2024-181, Greene County Battery storage |
199 MW | In study |
Greene, MO | SPP |
Mar 2025 | target 2029 |
Solar project GEN-2024-055, Vernon County Solar |
175 MW | In study |
Vernon, MO | SPP |
Oct 2024 | target 2029 |
Battery storage project GEN-2024-084, Lawrence County Battery storage |
167 MW | In study |
Lawrence, MO | SPP |
Oct 2024 | target 2028 |
Solar project GEN-2020-088, Jasper County Solar |
150 MW | Agreement signed |
Jasper, MO | SPP |
Apr 2020 | target 2028 |
Battery storage project GEN-2023-170, Chariton County Battery storage |
150 MW | In study |
Chariton, MO | SPP |
Oct 2023 | target 2028 |
Battery storage project GEN-2023-171, Jackson County Battery storage |
150 MW | In study |
Jackson, MO | SPP |
Oct 2023 | target 2028 |
Solar + storage project GEN-2020-072, Henry County Solar + storage |
150 MW | Agreement signed |
Henry, MO | SPP |
Apr 2020 | target 2029 |
Gas project GEN-2024-088, Greene County Gas |
145 MW | In study |
Greene, MO | SPP |
Oct 2024 | target 2027 |
Solar project GEN-2017-188, Barry County Solar |
130 MW | Agreement signed |
Barry, MO | SPP |
Nov 2017 | target 2026 |
Solar project GEN-2024-054, Cooper County Solar |
120 MW | In study |
Cooper, MO | SPP |
Oct 2024 | target 2029 |
Battery storage project GEN-2024-091, Jasper County Battery storage |
100 MW | In study |
Jasper, MO | SPP |
Oct 2024 | target 2028 |
Battery storage project GEN-2022-102, Clay County Battery storage |
100 MW | In study |
Clay, MO | SPP |
Jan 2023 | target 2027 |
Battery storage project GEN-2024-375, Saline County Battery storage |
100 MW | In study |
Saline, MO | SPP |
Mar 2025 | target 2029 |
Battery storage project GEN-2023-061, Jasper County Battery storage |
100 MW | In study |
Jasper, MO | SPP |
Oct 2023 | target 2029 |
Battery storage project GEN-2024-090, Clay County Battery storage |
100 MW | In study |
Clay, MO | SPP |
Oct 2024 | target 2028 |
Solar + storage project GEN-2021-077, Pettis County Solar + storage |
95.0 MW | In study |
Pettis, MO | SPP |
Apr 2021 | target 2027 |
Solar + storage project GEN-2022-100, Cooper County Solar + storage |
80.0 MW | In study |
Cooper, MO | SPP |
Mar 2023 | target 2028 |
Gas project GEN-2020-064, Jasper County Gas |
64.0 MW | Agreement signed |
Jasper, MO | SPP |
Apr 2020 | 2025 |
Battery storage project GEN-2018-031, Jackson County Battery storage |
50.0 MW | Agreement signed |
Jackson, MO | SPP |
May 2018 | target 2028 |
Other project GEN-2025-SR18, Jackson County Other |
50.0 MW | In study |
Jackson, MO | SPP |
Jun 2025 | target 2029 |
Battery storage project GEN-2021-042, Jackson County Battery storage |
50.0 MW | Agreement signed |
Jackson, MO | SPP |
Apr 2021 | target 2028 |
Gas project GEN-2020-061, Cass County Gas |
29.0 MW | Agreement signed |
Cass, MO | SPP |
Apr 2020 | target 2026 |