United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31146.6 GW
Active in queue10.1 GW68 requests
Agreement signed4,211 MW34 requests
Withdrawn31146.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

311 requests Β· page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AE1-222, Grundy County
Gas
2,563 MWWithdrawn / abandoned Grundy, ILPJM Sep 2018target 2022
Gas project AE1-213, Trumbull County
Gas
1,170 MWWithdrawn / abandoned Trumbull, OHPJM Sep 2018target 2023
Gas project AE2-013, Trumbull County
Gas
1,170 MWWithdrawn / abandoned Trumbull, OHPJM Nov 2018target 2023
Onshore wind project AE1-034, Atlantic County
Onshore wind
1,104 MWWithdrawn / abandoned Atlantic, NJPJM Jun 2018target 2024
Gas project AE2-007, City Of Chesapeake County
Gas
968 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Oct 2018target 2022
Gas project AD2-057, Trumbull County
Gas
940 MWWithdrawn / abandoned Trumbull, OHPJM Feb 2018target 2020
Offshore wind project AE2-024, Ocean County
Offshore wind
882 MWWithdrawn / abandoned Ocean, NJPJM Dec 2018target 2025
Offshore wind project AE1-238, Monmouth County
Offshore wind
816 MWWithdrawn / abandoned Monmouth, NJPJM Sep 2018target 2024
Offshore wind project AE1-067, City Of Virginia Beach County
Offshore wind
800 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Jul 2018target 2029
Offshore wind project AE1-066, City Of Virginia Beach County
Offshore wind
800 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Jul 2018target 2027
Offshore wind project AE1-065, City Of Virginia Beach County
Offshore wind
800 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Jul 2018target 2025
Solar + storage project AE1-214, Spencer County
Solar + storage
800 MWWithdrawn / abandoned Spencer, INPJM Sep 2018target 2023
Gas project AD2-171, Hunterdon County
Gas
700 MWWithdrawn / abandoned Hunterdon, NJPJM Mar 2018target 2023
Atlantic Shores Offshore Wind Project 1
Offshore wind
605 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Atlantic Shores Offshore Wind Project 1
Offshore wind
605 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Other project AE1-234, Chester County
Other
578 MWWithdrawn / abandoned Chester, PAPJM Sep 2018
Gas project AE2-012, Middlesex County
Gas
570 MWWithdrawn / abandoned Middlesex, NJPJM Nov 2018target 2023
Gas project AE1-119, Wood County
Gas
550 MWWithdrawn / abandoned Wood, OHPJM Sep 2018target 2022
Gas project AE1-121, Pittsylvania County
Gas
530 MWWithdrawn / abandoned Pittsylvania, VAPJM Sep 2018target 2022
Gas project AE1-122, Pittsylvania County
Gas
530 MWWithdrawn / abandoned Pittsylvania, VAPJM Sep 2018target 2023
Solar + storage project AE1-216, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Solar project AD2-197, Greensville County
Solar
500 MWWithdrawn / abandoned Greensville, VAPJM Mar 2018target 2021
Onshore wind project AE1-193, Henry County
Onshore wind
500 MWWithdrawn / abandoned Henry, ILPJM Sep 2018target 2021
Onshore wind project AE1-194, Will County
Onshore wind
500 MWWithdrawn / abandoned Will, ILPJM Sep 2018target 2021
Onshore wind project AE1-197, White County
Onshore wind
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2021
Solar project AE1-068, Greensville County
Solar
500 MWWithdrawn / abandoned Greensville, VAPJM Jul 2018target 2021
Onshore wind project AE1-195, Will County
Onshore wind
500 MWWithdrawn / abandoned Will, ILPJM Sep 2018target 2021
Hydro project AE1-058, Schuylkill County
Hydro
500 MWWithdrawn / abandoned Schuylkill, PAPJM Jul 2018target 2022
Solar + storage project AE1-215, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Gas project AD2-182, Marshall County
Gas
482 MWWithdrawn / abandoned Marshall, WVPJM Mar 2018target 2022
Offshore wind project AE2-023, Atlantic County
Offshore wind
445 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2024
Offshore wind project AE2-025, Ocean County
Offshore wind
445 MWWithdrawn / abandoned Ocean, NJPJM Dec 2018target 2026
South Bend Generating Station
Gas
410 MWWithdrawn / abandoned Armstrong, PAPJM Mar 2018target 2023
Solar project AE1-069, Greensville County
Solar
400 MWWithdrawn / abandoned Greensville, VAPJM Jul 2018target 2021
Onshore wind project AD2-136, Seneca County
Onshore wind
360 MWWithdrawn / abandoned Seneca, OHPJM Mar 2018target 2021
Solar + storage project AE1-198, Mchenry County
Solar + storage
357 MWWithdrawn / abandoned Mchenry, ILPJM Sep 2018target 2021
Solar project AE1-089, St. Joseph County
Solar
310 MWWithdrawn / abandoned St. Joseph, INPJM Aug 2018target 2021
Other project AD2-080, St. Joseph County
Other
309 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2018target 2020
Onshore wind project AE1-211, Jasper County
Onshore wind
302 MWWithdrawn / abandoned Jasper, INPJM Sep 2018target 2020
Solar project AE1-133, Alamance County
Solar
300 MWWithdrawn / abandoned Alamance, NCPJM Sep 2018target 2022
Onshore wind project AD2-142, Will County
Onshore wind
300 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Solar project AE1-047, Spotsylvania County
Solar
300 MWWithdrawn / abandoned Spotsylvania, VAPJM Jul 2018target 2021
Atlantic Shores Offshore Wind Project 1
Offshore wind
300 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Solar project AE1-236, Edgecombe County
Solar
290 MWWithdrawn / abandoned Edgecombe, NCPJM Sep 2018target 2022
Solar project AE1-206, Hanover County
Solar
285 MWWithdrawn / abandoned Hanover, VAPJM Sep 2018target 2022
Covert Generating Facility
Gas
285 MWWithdrawn / abandoned Van Buren, MIPJM Mar 2018target 2023
Solar project AE1-171, White County
Solar
280 MWWithdrawn / abandoned White, INPJM Sep 2018target 2022
Solar project AE1-241, Will County
Solar
250 MWWithdrawn / abandoned Will, ILPJM Sep 2018target 2021
Solar project AD2-206, Greensville County
Solar
250 MWWithdrawn / abandoned Greensville, VAPJM Mar 2018target 2020
Solar project AE1-189, Jay County
Solar
245 MWWithdrawn / abandoned Jay, INPJM Sep 2018target 2022
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)