United States β€Ί Grid β€Ί Interconnection queues β€Ί North Carolina

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in North Carolina, PJM

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown331,880 MW
Active in queue1,846 MW22 requests
Agreement signed1,308 MW13 requests
Withdrawn13711.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

33 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Desert Wind Farm
Onshore wind
208 MWOperating Pasquotank, NCPJM Feb 20102017
Timbermill Wind Farm
Onshore wind
189 MWOperating Perquimans, NCPJM Jul 20132024
Summit Farms Solar and Ranchland Solar
Solar
120 MWOperating Currituck, NCPJM Oct 20142018
Oak Solar
Solar
120 MWOperating Northampton, NCPJM Nov 20152024
Moccasin Creek Solar
Solar
100 MWOperating Edgecombe, NCPJM Mar 20162020
Aulander Holloman Solar Park
Solar
80.0 MWOperating Hertford, NCPJM Sep 20142019
Ablemarle Beach Solar
Solar
80.0 MWOperating Washington, NCPJM Apr 20152020
Harts Mill Solar
Solar
80.0 MWOperating Edgecombe, NCPJM Sep 20152020
Conetoe II Solar Park
Solar
80.0 MWOperating Edgecombe, NCPJM Apr 20142015
Gutenberg Solar
Solar
74.9 MWOperating Northampton, NCPJM Feb 20152019
Spuds Lane Solar Park
Solar
74.9 MWOperating Northampton, NCPJM Sep 20142018
Wilkinson Solar Energy Center
Solar
74.0 MWOperating Hyde, NCPJM Apr 20162019
Chestnut Solar
Solar
66.0 MWOperating Halifax, NCPJM Feb 20152019
Hawtree Creek
Solar
65.0 MWOperating Warren, NCPJM Aug 20162021
Domtar Paper Company Generating Units 7-10
Other
62.5 MWOperating Martin, NCPJM Jan 20062010
American Beech Solar
Solar
60.0 MWOperating Halifax, NCPJM Mar 20172025
American Beech Solar
Solar
60.0 MWOperating Alamance, NCPJM Oct 20162025
Oak Trail Solar
Solar
50.0 MWOperating Currituck, NCPJM Mar 20182023
Oak Trail Solar
Solar
50.0 MWOperating Currituck, NCPJM Mar 20192023
Kelford Solar Park
Solar
20.0 MWOperating Bertie, NCPJM Mar 20142015
Morgan's Corner Solar
Solar
20.0 MWOperating Pasquotank, NCPJM Apr 20122015
American Beech Solar
Solar
20.0 MWOperating Alamance, NCPJM Oct 20162025
Elizabeth City Solar Park
Solar
20.0 MWOperating Pasquotank, NCPJM Feb 20142014
Elizabeth City Solar
Solar
20.0 MWOperating Camden, NCPJM Feb 20162021
Aulander Holloman Solar Park
Solar
19.9 MWOperating Hertford, NCPJM Jun 20182020
Williamston Speight Solar
Solar
15.0 MWOperating Martin, NCPJM Sep 20142017
Colice Hall Solar
Solar
12.0 MWOperating Hertford, NCPJM Mar 20192023
Whitakers Solar Park
Solar
12.0 MWOperating Nash, NCPJM Mar 20142015
Chestnut Solar
Solar
8.9 MWOperating Halifax, NCPJM Apr 20152019
Colice Hall Solar
Solar
5.0 MWOperating Hertford, NCPJM Apr 20162023
Gutenberg Solar
Solar
5.0 MWOperating Northampton, NCPJM Apr 20152019
Solar project V4-068, Hertford County
Solar
5.0 MWOperating Hertford, NCPJM Jan 20102011
Kelford Solar Park
Solar
3.1 MWOperating Bertie, NCPJM Oct 20142015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)