🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in Southeast (non-ISO utilities) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown529112.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

529 requests · page 9 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 24
Other
48.0 MWOperating Southeast Jul 1998
Other project 24, Muhlenberg County
Other
48.0 MWOperating Muhlenberg, KYSoutheast Jul 1998
Moody AFB (+5.7 MW)
Solar
46.0 MWOperating Lowndes, GASoutheast 2020
Solar project 33, Polk County
Solar
45.0 MWOperating Polk, FLSoutheast Sep 2017target 2019
Solar project 149, Highlands County
Solar · Duke Energy Florida, LLC
45.0 MWOperating Highlands, FLSoutheast Jun 20162019
Dublin Biomass -GPS
Other
45.0 MWOperating Laurens, GASoutheast Dec 2023
Other project 198, Anderson County
Other
45.0 MWOperating Anderson, TNSoutheast Nov 2002
SR Hazlehurst III
Solar
44.0 MWOperating Jeff Davis, GASoutheast Dec 2023
Albany Green Energy
Other
44.0 MWOperating Dougherty, GASoutheast 2017
Other project 46, Cherokee County
Other
42.0 MWOperating Cherokee, NCSoutheast Jun 1999
Weyerhaeuser TG#2
Other
42.0 MWOperating Macon, GASoutheast Dec 2023
Other project 46
Other
42.0 MWOperating Southeast Jun 1999
Gas project 416, Lee County
Gas · FPL
42.0 MWOperating Lee, FLSoutheast Sep 20202024
Other project 22
Other
41.0 MWOperating Southeast Jul 1998
Other project 23
Other
41.0 MWOperating Southeast Jul 1998
Other project 22, Muhlenberg County
Other
41.0 MWOperating Muhlenberg, KYSoutheast Jul 1998
Other project 23, Muhlenberg County
Other
41.0 MWOperating Muhlenberg, KYSoutheast Jul 1998
GPC - Moody AFB Solar
Solar
40.3 MWOperating Lowndes, GASoutheast 2020
Other project 18, Anderson County
Other
40.0 MWOperating Anderson, TNSoutheast Jul 1998
Sonny Solar
Solar
40.0 MWOperating Elbert, GASoutheast Oct 20182024
Solar project 53, Hillsborough County
Solar
40.0 MWOperating Hillsborough, FLSoutheast Apr 2019target 2021
Other project 18
Other
40.0 MWOperating Southeast Jul 1998
Gas project 345, Polk County
Gas · Duke Energy Florida, LLC
40.0 MWOperating Polk, FLSoutheast Jan 20242025
Georgai Pacific - Brewton Co-Gen
Other
40.0 MWOperating Escambia, ALSoutheast 2017
Solar project 4894, Wilson County
Solar · Duke Energy Progress, LLC
40.0 MWOperating Wilson, NCSoutheast Sep 20132016
Dublin Biomass - SPFT
Gas
38.0 MWOperating Laurens, GASoutheast Dec 2023
Gas project 17112
Gas · Duke Energy Carolinas-0001674400
36.0 MWOperating Southeast Jun 20132015
Gas project 17113
Gas · Duke Energy Carolinas LLC
36.0 MWOperating Southeast Jun 20132014
Other project 200, Limestone County
Other
35.0 MWOperating Limestone, ALSoutheast Nov 2003
Other project 10, Horry County
Other · SCPSA
35.0 MWOperating Horry, SCSoutheast Apr 2001target 2005
Other project 199, Limestone County
Other
35.0 MWOperating Limestone, ALSoutheast Nov 2003
Gas project 50, Polk County
Gas · Duke Energy Florida, LLC
35.0 MWOperating Polk, FLSoutheast Jan 20071999
Gas project 25667, Richmond County
Gas · Duke Energy Progress, LLC
32.0 MWOperating Richmond, NCSoutheast Jan 20122012
Gas project 261, Morgan County
Gas
32.0 MWOperating Morgan, ALSoutheast Nov 2014
Other project 21
Other
31.0 MWOperating Southeast Jul 1998
MCLB Solar
Solar
31.0 MWOperating Dougherty, GASoutheast 2018
Other project 21, Jackson County
Other
31.0 MWOperating Jackson, ALSoutheast Jul 1998
Weyerhaeuser Port Wentworth
Gas
30.0 MWOperating Chatham, GASoutheast 2011
Nuclear project 174
Nuclear
30.0 MWOperating Southeast Jan 20162018
Simon Solar Farm
Solar
30.0 MWOperating Walton, GASoutheast Dec 2023
Stanton 1
Coal
30.0 MWOperating Orange, FLSoutheast May 20192020
Paw Paw Solar
Solar
30.0 MWOperating Taylor, GASoutheast 2016
Battery storage project 380, Suwannee County
Battery storage · FPL
30.0 MWOperating Suwannee, FLSoutheast Feb 20202021
Nuclear project 175
Nuclear · FPL
30.0 MWOperating Southeast Jan 20162020
Battery storage project 379, Columbia County
Battery storage · FPL
30.0 MWOperating Columbia, FLSoutheast Feb 20202021
Ft Benning Solar
Solar
29.8 MWOperating Russell, ALSoutheast 2015
Kings Bay Solar
Solar
29.3 MWOperating Camden, GASoutheast 2016
Fort Stewart Solar
Solar
29.3 MWOperating Liberty, GASoutheast 2016
Fort Gordon Solar
Solar
29.2 MWOperating Richmond, GASoutheast 2016
Other project 35, Berkeley County
Other
28.5 MWOperating Berkeley, SCSoutheast Jun 2014target 2016
Page 9 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)