🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

Moody AFB (+5.7 MW)

Moody AFB (+5.7 MW) is a 46.0 MW solar request built and operating in the Southeast interconnection queue, in Lowndes County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. Planning (completed)
  2. ConsentedMar 2020 (completed)
  3. Construction (completed)
  4. OperatingJun 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-736
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Lowndes County, Georgia
Technology
Solar: 46.0 MW
Total requested
46.0 MW
Study phase
Operational
Queue status
Operational
Agreement signed
5 March 2020
Came online
June 2020

Location

Marker shows the centre of Lowndes County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Lowndes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem