Withdrawn queue requests in West (non-ISO utilities) — page 83

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 83 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q130, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Apr 2010target 2012
Onshore wind project 136, Deer Lodge County
Onshore wind
20.0 MWWithdrawn / abandoned Deer Lodge, MTWest Apr 2011target 2012
Solar project 73, Pima County
Solar
19.9 MWWithdrawn / abandoned Pima, AZWest Feb 2020
Solar + storage project PIS076, Jefferson County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Jefferson, ORWest Jun 2024target 2028
Solar + storage project C3-090, Washington County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Washington, UTWest May 2023target 2028
Solar project 76, Pima County
Solar
19.9 MWWithdrawn / abandoned Pima, AZWest Feb 2020
Solar project 75, Pima County
Solar
19.9 MWWithdrawn / abandoned Pima, AZWest Feb 2020
Solar + storage project C4-055, Deschutes County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Deschutes, ORWest May 2024target 2028
Solar + storage project C3-095, Washington County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Washington, UTWest May 2023target 2028
Solar + storage project C4-056, Deschutes County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Deschutes, ORWest May 2024target 2028
Solar + storage project C4-057, Jefferson County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Jefferson, ORWest May 2024target 2028
Solar + storage project PIS074, Deschutes County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Deschutes, ORWest Jun 2024target 2028
Geothermal project 255, Elko County
Geothermal
19.9 MWWithdrawn / abandoned Elko, NVWest Jun 2008target 2013
Solar + storage project C4-074, Jefferson County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Jefferson, ORWest May 2024target 2028
Solar + storage project C3-093, Sevier County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Sevier, UTWest May 2023target 2028
Solar project 317, Weber County
Solar · Lakeview Cogeneration, LLC
19.9 MWWithdrawn / abandoned Weber, UTWest Feb 2010target 2012
Solar project C3-094, Sevier County
Solar · PacifiCorp
19.9 MWWithdrawn / abandoned Sevier, UTWest May 2023target 2028
Solar + storage project PIS073, Deschutes County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Deschutes, ORWest Jun 2024target 2028
Solar + storage project PIS077, Jefferson County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Jefferson, ORWest Jun 2024target 2028
Solar + storage project PIS075, Deschutes County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Deschutes, ORWest Jun 2024target 2028
Solar project GI-2021-11, Alamosa County
Solar
19.9 MWWithdrawn / abandoned Alamosa, COWest Aug 2021target 2022
Solar project C3-092, Tooele County
Solar · PacifiCorp
19.9 MWWithdrawn / abandoned Tooele, UTWest May 2023target 2028
Solar + storage project C3-085, Morrow County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Morrow, ORWest May 2023target 2029
Solar + storage project C3-088, Umatilla County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Umatilla, ORWest May 2023target 2028
Solar + storage project C4-054, Deschutes County
Solar + storage · PacifiCorp
19.9 MWWithdrawn / abandoned Deschutes, ORWest May 2024target 2028
Solar project 74, Pima County
Solar
19.9 MWWithdrawn / abandoned Pima, AZWest Feb 2020
Geothermal project Company LN, Esmeralda County
Geothermal
19.8 MWWithdrawn / abandoned Esmeralda, NVWest Apr 2021target 2021
Onshore wind project 184, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Onshore wind project 188, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Onshore wind project 154, Bonneville County
Onshore wind
19.8 MWWithdrawn / abandoned Bonneville, IDWest Aug 2007target 2009
Onshore wind project 189, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Geothermal project Company PE, Esmeralda County
Geothermal
19.8 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2024
Onshore wind project 337, Judith Basin County
Onshore wind
19.8 MWWithdrawn / abandoned Judith Basin, MTWest Dec 2017target 2019
Onshore wind project 185, Elmore County
Onshore wind
19.8 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Onshore wind project 127, Teton County
Onshore wind
19.5 MWWithdrawn / abandoned Teton, MTWest Oct 2010target 2011
Onshore wind project 47, Bonneville County
Onshore wind · Schwendiman Wind, LLC
19.5 MWWithdrawn / abandoned Bonneville, IDWest Oct 2004target 2005
Geothermal project S0032, Beaver County
Geothermal
19.2 MWWithdrawn / abandoned Beaver, UTWest Aug 2024target 2026
Other project 286, Malheur County
Other
19.0 MWWithdrawn / abandoned Malheur, ORWest Mar 2009target 2012
Solar project Q25, Pinal County
Solar
19.0 MWWithdrawn / abandoned Pinal, AZWest Oct 2011target 2012
Solar project Q204, Yuma County
Solar
19.0 MWWithdrawn / abandoned Yuma, AZWest Sep 2011target 2013
Solar + storage project Q80, Spokane County
Solar + storage
19.0 MWWithdrawn / abandoned Spokane, WAWest target 2026
Onshore wind project 102, Teton County
Onshore wind
18.9 MWWithdrawn / abandoned Teton, MTWest Jan 2009target 2010
Onshore wind project 48, Teton County
Onshore wind
18.9 MWWithdrawn / abandoned Teton, MTWest Jun 2006
Onshore wind project Q88, Navajo County
Onshore wind
18.9 MWWithdrawn / abandoned Navajo, AZWest Dec 2009target 2010
Onshore wind project 50, Teton County
Onshore wind
18.9 MWWithdrawn / abandoned Teton, MTWest Jun 2006target 2010
Solar + storage project 117, Apache County
Solar + storage
18.8 MWWithdrawn / abandoned Apache, AZWest Mar 2022target 2023
Other project 41, Ada County
Other
18.0 MWWithdrawn / abandoned Ada, IDWest May 2001target 2001
Onshore wind project 286, Chouteau County
Onshore wind
18.0 MWWithdrawn / abandoned Chouteau, MTWest Jun 2016target 2017
Other project 637, Salt Lake County
Other
18.0 MWWithdrawn / abandoned Salt Lake, UTWest Dec 2014target 2015
Onshore wind project 190, Elmore County
Onshore wind
18.0 MWWithdrawn / abandoned Elmore, IDWest Oct 2006target 2007
Page 83 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)