πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR + STORAGE Β· WEST

Solar + storage project C3-093, Sevier County

Solar + storage project C3-093, Sevier County is a 19.9 MW solar + storage request withdrawn in the West interconnection queue, in Sevier County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C3-093
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp
Connection point (POI)
Sigurd substation
Location
Sevier County, Utah
Technology
Solar: 19.9 MW Β· Battery
Total requested
19.9 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
12 May 2023
Proposed online date
May 2028

Location

Marker shows the centre of Sevier County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Sevier County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem