Solar project 589, Sevier County

Solar project 589, Sevier County is a 80.0 MW solar request built and operating in the West interconnection queue, in Sevier County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Jul 2014 (completed)
  2. ConsentedJan 2016 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
589
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Sigurd Solar, LLC
Connection point (POI)
Sigurd substation
Location
Sevier County, Utah
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Energy only (ERIS)
Study phase
IA signed 1/29/16, Suspended 3/1/2017, Unsuspended 5/31/18
Queue status
Operational
Entered queue
3 July 2014
Agreement signed
29 January 2016
Proposed online date
October 2020

Location

Marker shows the centre of Sevier County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Sevier County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem