SOLAR · WESTSolar project 589, Sevier County
Solar project 589, Sevier County is a 80.0 MW solar request built and operating in the West interconnection queue, in Sevier County, Utah, connecting to PacifiCorp.
Request details
- Queue ID
- 589
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Sigurd Solar, LLC
- Connection point (POI)
- Sigurd substation
- Location
- Sevier County, Utah
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA signed 1/29/16, Suspended 3/1/2017, Unsuspended 5/31/18
- Queue status
- Operational
- Entered queue
- 3 July 2014
- Agreement signed
- 29 January 2016
- Proposed online date
- October 2020
Location
Marker shows the centre of Sevier County; the queue data does not give exact sites.
Other requests in Sevier County
- Battery storage project S0016, Sevier CountyBattery storage · 80.0 MW · agreement signed
- Geothermal project T2-004, Sevier CountyGeothermal · 20.0 MW · in study
- Gas project 403, Sevier CountyGas · 525 MW · withdrawn
- Battery storage project C3-152, Sevier CountyBattery storage · 500 MW · withdrawn
- Coal project 121, Sevier CountyCoal · 270 MW · withdrawn
- Solar project 602, Sevier CountySolar · 80.0 MW · withdrawn
- Solar + storage project C3-143, Sevier CountySolar + storage · 80.0 MW · withdrawn
- Geothermal project C4-003, Sevier CountyGeothermal · 20.0 MW · withdrawn
- Solar + storage project C3-093, Sevier CountySolar + storage · 19.9 MW · withdrawn
- Solar project C3-094, Sevier CountySolar · 19.9 MW · withdrawn
- Solar project 625, Sevier CountySolar · 1.0 MW · withdrawn
- Solar project 546, Sevier CountySolar · 0.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem