United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in ERCOT (Texas) (2023 requests) β€” page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown35676.0 GW
Active in queue76.0 GW356 requests
Agreement signed24.2 GW103 requests
Withdrawn8516.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

356 requests Β· page 8 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Hidden Lakes BESS
Battery storage Β· SBESS TX 6 LLC
9.9 MWAgreement signed Galveston, TXERCOT Jun 2023target 2026
Gears BESS
Battery storage Β· Regis Gears-Harris LLC
9.9 MWAgreement signed Harris, TXERCOT Jun 2023target 2026
Chocolate Bayou BESS
Battery storage Β· Concurrent Holdco. , LLC.
9.9 MWIn study ERCOT Aug 2023target 2026
Panther Creek 2 Repower
Onshore wind Β· Panther Creek Wind Farm I&II, LLC
8.0 MWIn study Glasscock, TXERCOT Jun 2023target 2026
CPS Rio Nogales CT301 Rotor Replacement
Gas Β· CPS Energy
3.1 MWAgreement signed Guadalupe, TXERCOT Jul 2023target 2025
Champion Wind Repower
Onshore wind Β· Champion Wind Farm, LLC
0.3 MWAgreement signed Nolan, TXERCOT Sep 2023target 2025
Page 8 of 8

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)