United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 76

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 76 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Milton
Solar
14.9 MWWithdrawn / abandoned Sussex, DEPJM Aug 2011target 2018
Solar project AG2-654, Armstrong County
Solar · IMG Solar LLC
14.7 MWWithdrawn / abandoned Armstrong, PAPJM Jan 2025target 2022
Solar project AG2-111, Campbell County
Solar · Koala Solar, LLC
14.5 MWWithdrawn / abandoned Campbell, VAPJM Feb 2025target 2023
Onshore wind project X2-100, Salem County
Onshore wind
14.4 MWWithdrawn / abandoned Salem, NJPJM Jul 2011target 2012
Gas project AH1-132, Frederick County
Gas
14.4 MWWithdrawn / abandoned Frederick, VAPJM Aug 2021target 2022
Gas project AC2-131, Chesterfield County
Gas
14.3 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2017target 2017
Solar project AF2-373, Halifax County
Solar
14.3 MWWithdrawn / abandoned Halifax, VAPJM Mar 2020target 2022
SH-Mehrrin Solar
Solar · SH-Mehrrin LLC
14.2 MWWithdrawn / abandoned Southampton, VAPJM Sep 2020target 2022
Solar project AG2-178, Fauquier County
Solar
14.1 MWWithdrawn / abandoned Fauquier, VAPJM Feb 2021target 2022
Solar project AG1-468, Henry County
Solar
14.0 MWWithdrawn / abandoned Henry, VAPJM Sep 2020target 2022
Solar project AB2-167, Worcester County
Solar
14.0 MWWithdrawn / abandoned Worcester, MDPJM Apr 2016target 2017
Brunner Island #1
Coal
14.0 MWWithdrawn / abandoned York, PAPJM Feb 2001target 2002
Hydro project AG2-505, Garrett County
Hydro · Fairlawn Hydroelectric Company, LLC
14.0 MWWithdrawn / abandoned Garrett, MDPJM Mar 2025target 2023
Brunner Island #2
Coal
14.0 MWWithdrawn / abandoned York, PAPJM Feb 2001target 2002
Solar project AG1-459, Washington County
Solar
14.0 MWWithdrawn / abandoned Washington, MDPJM Sep 2020target 2023
Solar project Z1-076, Worcester County
Solar
14.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2018
Battery storage project AG1-215, Nottoway County
Battery storage
14.0 MWWithdrawn / abandoned Nottoway, VAPJM Sep 2020target 2022
Onshore wind project R21, Hardy County
Onshore wind
14.0 MWWithdrawn / abandoned Hardy, WVPJM Oct 2006target 2010
Solar project AB2-176, Mecklenburg County
Solar
14.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Apr 2016target 2017
Other project R98, Henrico County
Other
14.0 MWWithdrawn / abandoned Henrico, VAPJM Jan 2007target 2008
Solar project AG2-090, Somerset County
Solar · Neptune Solar LLC
14.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2025target 2023
Solar project AD2-200, Mecklenburg County
Solar
14.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2018target 2019
Hydro project U1-070, Allegheny County
Hydro
14.0 MWWithdrawn / abandoned Allegheny, PAPJM Apr 2008target 2015
Other project AD2-103, Baltimore County
Other
14.0 MWWithdrawn / abandoned Baltimore, MDPJM Mar 2018target 2019
Solar project U3-022, Cumberland County
Solar
14.0 MWWithdrawn / abandoned Cumberland, NJPJM Sep 2008target 2009
Solar project AG1-466, Orange County
Solar
14.0 MWWithdrawn / abandoned Orange, VAPJM Sep 2020target 2022
Battery storage project V4-003, New Castle County
Battery storage
14.0 MWWithdrawn / abandoned New Castle, DEPJM Nov 2009target 2010
Hydro project U4-007, Garrett County
Hydro
14.0 MWWithdrawn / abandoned Garrett, MDPJM Nov 2008target 2013
Solar project AA2-036, Dorchester County
Solar
14.0 MWWithdrawn / abandoned Dorchester, MDPJM Jan 2015target 2015
Gas project O37, Kanawha County
Gas
14.0 MWWithdrawn / abandoned Kanawha, WVPJM Jun 2005target 2006
Barberton Solar
Solar
14.0 MWWithdrawn / abandoned Summit, OHPJM Jul 2011target 2014
Solar project AB2-144, Frederick County
Solar
13.8 MWWithdrawn / abandoned Frederick, MDPJM Apr 2016target 2017
Solar project X4-030, Sandusky County
Solar
13.8 MWWithdrawn / abandoned Sandusky, OHPJM Dec 2011target 2013
Sand Flat Road Solar Project
Solar
13.8 MWWithdrawn / abandoned Garrett, MDPJM Apr 2019target 2023
Onshore wind project K12, Somerset County
Onshore wind
13.6 MWWithdrawn / abandoned Somerset, PAPJM Jul 2003target 2005
Solar project AF1-286, Bradford County
Solar
13.6 MWWithdrawn / abandoned Bradford, PAPJM Sep 2019target 2026
Solar project AG1-036, Bertie County
Solar
13.5 MWWithdrawn / abandoned Bertie, NCPJM Jun 2020target 2021
Other project AA2-044, Cumberland County
Other
13.5 MWWithdrawn / abandoned Cumberland, NJPJM Feb 2015target 2016
Solar project AF2-148, Huntingdon County
Solar
13.5 MWWithdrawn / abandoned Huntingdon, PAPJM Mar 2020target 2023
Gas project C16, Clearfield County
Gas
13.5 MWWithdrawn / abandoned Clearfield, PAPJM Mar 2000
Solar project AF1-255, Bedford County
Solar
13.5 MWWithdrawn / abandoned Bedford, PAPJM Sep 2019target 2019
Solar project AB2-142, Caroline County
Solar
13.4 MWWithdrawn / abandoned Caroline, MDPJM Apr 2016target 2018
Solar project AG1-190, Burlington County
Solar
13.2 MWWithdrawn / abandoned Burlington, NJPJM Sep 2020target 2021
Solar project AF2-147, Mifflin County
Solar
13.1 MWWithdrawn / abandoned Mifflin, PAPJM Mar 2020target 2023
Solar project AI1-036, Somerset County
Solar
13.0 MWWithdrawn / abandoned Somerset, PAPJM Apr 2022target 2028
Gas project AF2-155, Prince George's County
Gas
13.0 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2020target 2021
East Windsor Solar Farm
Solar
13.0 MWWithdrawn / abandoned Mercer, NJPJM Sep 2010target 2014
Other project W3-161, Fayette County
Other
13.0 MWWithdrawn / abandoned Fayette, WVPJM Oct 2010target 2013
Solar project AH1-371, Allegheny County
Solar
13.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2021target 2024
Solar project V4-077, Mifflin County
Solar
13.0 MWWithdrawn / abandoned Mifflin, PAPJM Jan 2010target 2014
Page 76 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)