United States › Grid › Interconnection queues › Kentucky

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Kentucky — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown33364.0 GW
Active in queue21.5 GW134 requests
Agreement signed7,260 MW36 requests
Withdrawn33364.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

333 requests · page 7 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AF2-308, Hardin County
Battery storage
28.0 MWWithdrawn / abandoned Hardin, KYPJM Mar 2020target 2023
Solar project AG1-381, Montgomery County
Solar
27.0 MWWithdrawn / abandoned Montgomery, KYPJM Sep 2020target 2023
Flat Top Solar
Battery storage
26.0 MWWithdrawn / abandoned Barren, KYPJM Mar 2020target 2027
Battery storage project AE2-208, Perry County
Battery storage
25.0 MWWithdrawn / abandoned Perry, KYPJM Mar 2019target 2021
Battery storage project 488, Christian County
Battery storage
25.0 MWWithdrawn / abandoned Christian, KYSoutheast Nov 2021target 2025
Battery storage project J1409, Henderson County
Battery storage
25.0 MWWithdrawn / abandoned Henderson, KYMISO Apr 2019target 2023
Solar project LGE-GIS-2017-004, Harrison County
Solar
25.0 MWWithdrawn / abandoned Harrison, KYSoutheast Jun 2017target 2019
Solar project AH1-529, Bourbon County
Solar
24.0 MWWithdrawn / abandoned Bourbon, KYPJM Sep 2021target 2025
Sunflower Prairie
Battery storage · Sunflower Prairie Solar Project, LLC
22.0 MWWithdrawn / abandoned Mclean, KYPJM Sep 2020target 2024
Solar project AF2-017, Pike County
Solar
20.0 MWWithdrawn / abandoned Pike, KYPJM Oct 2019target 2021
Solar + storage project AH1-382, Mercer County
Solar + storage
20.0 MWWithdrawn / abandoned Mercer, KYPJM Sep 2021target 2025
Solar project AH1-136
Solar · Big Sandy Renewables, LLC
20.0 MWWithdrawn / abandoned KYPJM Mar 2025target 2024
Solar project AG2-513, Larue County
Solar
20.0 MWWithdrawn / abandoned Larue, KYPJM Mar 2021target 2023
Solar project AH1-281, Nelson County
Solar · Soltage KY DevCo, LLC
20.0 MWWithdrawn / abandoned Nelson, KYPJM Mar 2025target 2024
Solar project AF2-419, Boyle County
Solar
20.0 MWWithdrawn / abandoned Boyle, KYPJM Mar 2020target 2021
Solar project AF2-420, Boyle County
Solar
20.0 MWWithdrawn / abandoned Boyle, KYPJM Mar 2020target 2021
Solar project AG2-671, Montgomery County
Solar
19.9 MWWithdrawn / abandoned Montgomery, KYPJM Mar 2021target 2023
Other project X2-090, Martin County
Other
19.0 MWWithdrawn / abandoned Martin, KYPJM Jul 2011target 2012
Solar project AG2-512, Marion County
Solar
17.5 MWWithdrawn / abandoned Marion, KYPJM Mar 2021target 2023
Other project G508, Ballard County
Other
15.0 MWWithdrawn / abandoned Ballard, KYMISO Mar 2005target 2006
Other project W2-062, Perry County
Other
12.1 MWWithdrawn / abandoned Perry, KYPJM Jul 2010target 2012
Solar project AH1-464, Montgomery County
Solar
12.0 MWWithdrawn / abandoned Montgomery, KYPJM Sep 2021target 2022
Solar project LGE-GIS-2017-005, Harrison County
Solar
10.0 MWWithdrawn / abandoned Harrison, KYSoutheast Aug 2017target 2018
Other project LGE-GIS-2008-003, Henry County
Other
9.0 MWWithdrawn / abandoned Henry, KYSoutheast Nov 2008target 2010
Other project LGE-GIS-2008-004, Lincoln County
Other
6.0 MWWithdrawn / abandoned Lincoln, KYSoutheast Nov 2008target 2010
Other project LGE-GIS-2008-002, Ohio County
Other
5.0 MWWithdrawn / abandoned Ohio, KYSoutheast Nov 2008target 2010
Solar + storage project AG1-077, Magoffin County
Solar + storage
3.7 MWWithdrawn / abandoned Magoffin, KYPJM Jul 2020target 2022
Battery storage project AF2-098, Grant County
Battery storage
3.5 MWWithdrawn / abandoned Grant, KYPJM Feb 2020target 2020
Hydro project LGE-GIS-2018-001, Estill County
Hydro
3.0 MWWithdrawn / abandoned Estill, KYSoutheast Aug 2018target 2018
Solar project AC1-138, Boone County
Solar
2.5 MWWithdrawn / abandoned Boone, KYPJM Oct 2016target 2017
Solar project AC1-136, Johnson County
Solar
2.0 MWWithdrawn / abandoned Johnson, KYPJM Oct 2016target 2017
Solar project AC1-137, Boone County
Solar
1.9 MWWithdrawn / abandoned Boone, KYPJM Oct 2016target 2017
Hydro project LGE-GIS-2018-008, Estill County
Hydro
1.5 MWWithdrawn / abandoned Estill, KYSoutheast Oct 2018target 2018
Page 7 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)