United States › Grid › Interconnection queues › Kentucky
BATTERY STORAGE · PJMSunflower Prairie
Sunflower Prairie is a 22.0 MW battery storage request withdrawn in the PJM interconnection queue, in Mclean County, Kentucky, connecting to EKPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-406
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Developer
- Sunflower Prairie Solar Project, LLC
- Connection point (POI)
- Walnut Grove-Asahi 69 kV
- Location
- Mclean County, Kentucky
- Technology
- Battery: 22.0 MW
- Total requested
- 22.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- September 2024
- Withdrawn
- November 2025
Location
Marker shows the centre of Mclean County; the queue data does not give exact sites.
Other requests in Mclean County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem