United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 66

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 66 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G123, Murray County
Other
2.0 MWWithdrawn / abandoned Murray, MNMISO Sep 2001target 2003
Onshore wind project G372, Pope County
Onshore wind
1.7 MWWithdrawn / abandoned Pope, MNMISO Nov 2003target 2009
Onshore wind project J1803, Houghton County
Onshore wind
1.6 MWWithdrawn / abandoned Houghton, MIMISO Jun 2020target 2021
Onshore wind project G419, Lyon County
Onshore wind
1.5 MWWithdrawn / abandoned Lyon, IAMISO Mar 2004target 2005
Gas project G498, Richland County
Gas
1.1 MWWithdrawn / abandoned Richland, OHMISO Feb 2005target 2005
Onshore wind project J1126, Tuscola County
Onshore wind
1.1 MWWithdrawn / abandoned Tuscola, MIMISO Mar 2018target 2020
Onshore wind project G596, Morrison County
Onshore wind
1.0 MWWithdrawn / abandoned Morrison, MNMISO Feb 2006target 2009
Onshore wind project G450, Rolette County
Onshore wind
1.0 MWWithdrawn / abandoned Rolette, NDMISO Aug 2004target 2006
Other project G124, Murray County
Other
1.0 MWWithdrawn / abandoned Murray, MNMISO Sep 2001target 2005
Onshore wind project MPC03300, Cass County
Onshore wind
0.8 MWWithdrawn / abandoned Cass, NDMISO Nov 2016target 2018
Other project G582, Eau Claire County
Other
0.5 MWWithdrawn / abandoned Eau Claire, WIMISO Dec 2005target 2010
Page 66 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)