United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 59

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 59 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project C2-183, Harney County
Solar + storage
80.0 MWWithdrawn / abandoned Harney, ORWest May 2022target 2026
Solar + storage project 537, Harney County
Solar + storage
80.0 MWWithdrawn / abandoned Harney, ORWest Jun 2018
Solar project 601, Emery County
Solar
80.0 MWWithdrawn / abandoned Emery, UTWest Aug 2014target 2016
Solar + storage project 801, Natrona County
Solar + storage · Dinosolar, LLC
80.0 MWWithdrawn / abandoned Natrona, WYWest Sep 2016target 2019
Solar project 435, Crook County
Solar
80.0 MWWithdrawn / abandoned Crook, ORWest Aug 2012target 2014
Onshore wind project GI-1210, Blaine County
Onshore wind
80.0 MWWithdrawn / abandoned Blaine, MTWest Aug 2012target 2014
Solar + storage project 1188, Crook County
Solar + storage
80.0 MWWithdrawn / abandoned Crook, ORWest Nov 2019target 2022
Solar project 1136, Klamath County
Solar
80.0 MWWithdrawn / abandoned Klamath, ORWest May 2019target 2022
Solar + storage project 428, Big Horn County
Solar + storage
80.0 MWWithdrawn / abandoned Big Horn, MTWest May 2022target 2025
Onshore wind project 90, Golden Valley County
Onshore wind
80.0 MWWithdrawn / abandoned Golden Valley, MTWest May 2008target 2011
Solar project 448, Crook County
Solar
80.0 MWWithdrawn / abandoned Crook, ORWest Dec 2012target 2015
Solar project Company 176, Clark County
Solar
80.0 MWWithdrawn / abandoned Clark, NVWest Mar 2019target 2023
Battery storage project 148, Pima County
Battery storage
80.0 MWWithdrawn / abandoned Pima, AZWest Dec 2022target 2026
Solar project GI-2018-20, Weld County
Solar
80.0 MWWithdrawn / abandoned Weld, COWest May 2018target 2020
Solar + storage project 1033, Harney County
Solar + storage
80.0 MWWithdrawn / abandoned Harney, ORWest May 2018target 2020
Solar project 1138, Klamath County
Solar
80.0 MWWithdrawn / abandoned Klamath, ORWest May 2019target 2022
Solar project 813, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Oct 2016target 2019
Onshore wind project 148, Stillwater County
Onshore wind
80.0 MWWithdrawn / abandoned Stillwater, MTWest Jan 2012target 2014
Onshore wind project 221-A, Summit County
Onshore wind
80.0 MWWithdrawn / abandoned Summit, UTWest May 2008target 2010
Solar project 447, Yellowstone County
Solar
80.0 MWWithdrawn / abandoned Yellowstone, MTWest Sep 2023target 2027
Solar project BHCT G30, Pueblo County
Solar
80.0 MWWithdrawn / abandoned Pueblo, COWest Aug 2021target 2024
Onshore wind project 128, Beaver County
Onshore wind · Clipper Windpower Development Company, Inc
80.0 MWWithdrawn / abandoned Beaver, UTWest Mar 2007target 2009
Onshore wind project GI-0211, Dickey County
Onshore wind
80.0 MWWithdrawn / abandoned Dickey, NDWest Jun 2002
Solar project 588, San Juan County
Solar
80.0 MWWithdrawn / abandoned San Juan, UTWest Jul 2014target 2016
Solar project 71, Pima County
Solar
80.0 MWWithdrawn / abandoned Pima, AZWest Jan 2020target 2022
Solar project 1019, Linn County
Solar
80.0 MWWithdrawn / abandoned Linn, ORWest Apr 2018target 2021
Onshore wind project 327, Stillwater County
Onshore wind
80.0 MWWithdrawn / abandoned Stillwater, MTWest Jul 2017target 2021
Onshore wind project 868, Rich County
Onshore wind
80.0 MWWithdrawn / abandoned Rich, UTWest Apr 2017target 2019
Solar project 924, Klamath County
Solar
80.0 MWWithdrawn / abandoned Klamath, ORWest Aug 2017target 2019
Onshore wind project 867, Carbon County
Onshore wind
80.0 MWWithdrawn / abandoned Carbon, UTWest Apr 2017target 2019
Solar + storage project 1013, Converse County
Solar + storage
80.0 MWWithdrawn / abandoned Converse, WYWest Mar 2018target 2020
Onshore wind project 45, Kittitas County
Onshore wind
80.0 MWWithdrawn / abandoned Kittitas, WAWest Oct 2015target 2029
Solar project 610, Juab County
Solar
80.0 MWWithdrawn / abandoned Juab, UTWest Aug 2014target 2016
Onshore wind project 52, Sweet Grass County
Onshore wind
80.0 MWWithdrawn / abandoned Sweet Grass, MTWest Sep 2006
Solar + storage project 915, Klamath County
Solar + storage
80.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2017target 2019
Onshore wind project 855, Converse County
Onshore wind
80.0 MWWithdrawn / abandoned Converse, WYWest Mar 2017target 2019
Solar + storage project 1162, Crook County
Solar + storage
80.0 MWWithdrawn / abandoned Crook, ORWest Sep 2019target 2022
Solar project TCS-16, Lincoln County
Solar
80.0 MWWithdrawn / abandoned Lincoln, WYWest Oct 2018target 2023
Battery storage project 415, Yellowstone County
Battery storage
80.0 MWWithdrawn / abandoned Yellowstone, MTWest Sep 2021target 2024
Solar + storage project 69, Cochise County
Solar + storage
80.0 MWWithdrawn / abandoned Cochise, AZWest Jan 2020target 2022
Solar + storage project 1133, Klamath County
Solar + storage
80.0 MWWithdrawn / abandoned Klamath, ORWest May 2019target 2022
Onshore wind project G0228, Wasco County
Onshore wind
80.0 MWWithdrawn / abandoned Wasco, ORWest Jun 2006target 2008
Onshore wind project 9, Douglas County
Onshore wind
80.0 MWWithdrawn / abandoned Douglas, WAWest Dec 2007target 2010
Solar + storage project PIS006, Bingham County
Solar + storage
80.0 MWWithdrawn / abandoned Bingham, IDWest May 2022target 2025
Solar project Company 145, Clark County
Solar
80.0 MWWithdrawn / abandoned Clark, NVWest Sep 2015target 2018
Onshore wind project 427, Sweetwater County
Onshore wind · OM Power 1, LLC
80.0 MWWithdrawn / abandoned Sweetwater, WYWest Jul 2012target 2015
Onshore wind project 440, Carbon County
Onshore wind
80.0 MWWithdrawn / abandoned Carbon, WYWest Oct 2012target 2016
Solar project 46, Pima County
Solar
80.0 MWWithdrawn / abandoned Pima, AZWest Jul 2016target 2019
Onshore wind project 18-07261, Larimer County
Onshore wind
80.0 MWWithdrawn / abandoned Larimer, COWest Jul 2018target 2019
Solar project 541, San Juan County
Solar
80.0 MWWithdrawn / abandoned San Juan, UTWest Dec 2013target 2015
Page 59 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)