United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 5 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 33170, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Mar 2019
Gas project 43466, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Aug 2019
New Scotland BESS (NYISO-C24-045)
Battery storage
1,350 MWWithdrawn / abandoned Albany, NYISO-NE Dec 2024target 2027
Gas project 30612, Wake County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Wake, NCSoutheast Feb 2019
Gas project 43484, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Aug 2019
New Scotland BESS
Battery storage · Eden Renewables
1,350 MWWithdrawn / abandoned Albany, NYNYISO Nov 2023
New Scotland BES 1 and 2
Battery storage · Eden Renewables
1,350 MWWithdrawn / abandoned Albany, NYNYISO Mar 2023
Gas project 72278, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Mar 2020
Gas project 43510, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Aug 2019
Vineyard Northeast 1
Offshore wind · Vineyard Northeast
1,350 MWWithdrawn / abandoned Kings, NYNYISO Sep 2022
New Scotland BESS
Battery storage · Eden DevCo
1,350 MWWithdrawn / abandoned Albany, NYNYISO Feb 2024
Gas project 43498, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Aug 2019
New Scotland BESS
Battery storage · New Scotland BESS
1,350 MWWithdrawn / abandoned Albany, NYNYISO Aug 2024
Gas project 113970, Person County
Gas · Duke Energy Progress, LLC
1,350 MWWithdrawn / abandoned Person, NCSoutheast Mar 2020
Vineyard Northeast 2
Offshore wind · Vineyard Northeast LLC
1,345 MWWithdrawn / abandoned Kings, NYNYISO Oct 2022
Other project 129, Clay County
Other
1,340 MWWithdrawn / abandoned Clay, MSSoutheast Nov 2000
Gas project AE2-167, Doddridge County
Gas
1,335 MWWithdrawn / abandoned Doddridge, WVPJM Mar 2019target 2023
Vineyard Mid-Atlantic 3
Offshore wind · Vineyard Mid-Atlantic LLC
1,330 MWWithdrawn / abandoned Nassau, NYNYISO Nov 2022
Vineyard Mid-Atlantic 2
Offshore wind · Vineyard Mid-Atlantic
1,330 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2022
NY Wind - New Bridge Road
Offshore wind · Bay State Wind
1,325 MWWithdrawn / abandoned Nassau, NYNYISO Jul 2020
Offshore wind
Offshore wind
1,320 MWWithdrawn / abandoned MAISO-NE Apr 2021target 2027
Gas project U2-098, Middlesex County
Gas
1,320 MWWithdrawn / abandoned Middlesex, NJPJM Jul 2008target 2013
Cosw Bceh
Offshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
Bluepoint Wind 2
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Long Island Wind
Offshore wind · Bay State Wind
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
Community OSW Barrett 3
Onshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Nassau, NYNYISO Dec 2023
COSW Barrett
Offshore wind · Community Offshore Wind, LLC
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Bluepoint Wind 1
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Sep 2023
Queensboro Renewable Express Circuit A
Onshore wind · Queensboro Development, LLC
1,310 MWWithdrawn / abandoned Queens, NYNYISO Aug 2024
Queensboro Renewable Express Circuit A
Offshore wind · Queensboro Development, LLC
1,310 MWWithdrawn / abandoned Queens, NYNYISO Dec 2022
Attentive Energy 1
Offshore wind · Attentive Energy
1,310 MWWithdrawn / abandoned Suffolk, NYNYISO Jun 2022
Blue Point Wind 3A
Onshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Richmond, NYNYISO Sep 2023
Bluepoint Wind 2
Offshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Kings, NYNYISO Sep 2023
Queensboro B
Onshore wind · Light & Power Development
1,310 MWWithdrawn / abandoned Queens, NYNYISO Nov 2023
Attentive Energy 2
Offshore wind · Attentive Energy
1,310 MWWithdrawn / abandoned Kings, NYNYISO Jun 2022
Bluepoint Wind 3B
Onshore wind · Bluepoint Wind LLC
1,310 MWWithdrawn / abandoned Richmond, NYNYISO Sep 2023
Blue Sky Interconnect 1
Offshore wind · Blue Sky Interconnect, LLC.
1,310 MWWithdrawn / abandoned Kings, NYNYISO Mar 2023
Offshore wind
Offshore wind
1,309 MWWithdrawn / abandoned MAISO-NE Oct 2023target 2030
Larrabee 230 kV IV
Offshore wind · Atlantic Shores Offshore Wind Project 2, LLC
1,300 MWWithdrawn / abandoned Monmouth, NJPJM Sep 2021target 2029
EI Steinway 2
Offshore wind · Beacon Wind LLC
1,300 MWWithdrawn / abandoned Queens, NYNYISO May 2020
1300MW Sickler-Schultz
Gas · Calpine Energy Services, L.P.
1,300 MWWithdrawn / abandoned Benton, WAWest May 2001target 2005
Competitive Power Venture
Gas · Newport Northwest, LLC
1,300 MWWithdrawn / abandoned Whatcom, WAWest Mar 2001target 2005
Hydro project Q499, Riverside County
Hydro
1,300 MWWithdrawn / abandoned Riverside, CAWest Mar 2023target 2027
EI Steinway 1
Offshore wind · Beacon Wind LLC
1,300 MWWithdrawn / abandoned Queens, NYNYISO Sep 2024
Solar + storage project G0966, Umatilla County
Solar + storage
1,300 MWWithdrawn / abandoned Umatilla, ORWest Oct 2023target 2032
Coal project S12, Adams County
Coal
1,300 MWWithdrawn / abandoned Adams, OHPJM Mar 2007target 2014
EI Steinway 1
Offshore wind · Beacon Wind LLC
1,300 MWWithdrawn / abandoned Queens, NYNYISO May 2020
Kootenai Generation
Gas
1,300 MWWithdrawn / abandoned Kootenai, WAWest Mar 2001target 2005
Solar + storage project G0962, Morrow County
Solar + storage
1,300 MWWithdrawn / abandoned Morrow, ORWest Oct 2023target 2028
Grant Generation
Gas · Grant Generation, LLC
1,300 MWWithdrawn / abandoned Grant, WAWest Apr 2001target 2005
Page 5 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)