United States › Grid › Interconnection queues › Montana
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Montana — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project 89, Meagher County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 146, Sweet Grass County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 287, Chouteau County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 151, Wheatland County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project 445, Fergus County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 160, Sweet Grass County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar project 159, Big Horn County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 394, Golden Valley County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 344, Teton County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1213, Valley County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 150, Big Horn County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 275, Sweet Grass County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project J1766, Fallon County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 47, Liberty County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 136, Deer Lodge County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project 337, Judith Basin County Onshore wind |
19.8 MW | Withdrawn / abandoned |
| Onshore wind project G994, Wibaux County Onshore wind |
19.5 MW | Withdrawn / abandoned |
| Onshore wind project 127, Teton County Onshore wind |
19.5 MW | Withdrawn / abandoned |
| Onshore wind project 102, Teton County Onshore wind |
18.9 MW | Withdrawn / abandoned |
| Onshore wind project 48, Teton County Onshore wind |
18.9 MW | Withdrawn / abandoned |
| Onshore wind project 50, Teton County Onshore wind |
18.9 MW | Withdrawn / abandoned |
| Onshore wind project 286, Chouteau County Onshore wind |
18.0 MW | Withdrawn / abandoned |
| Onshore wind project 154, Madison County Onshore wind |
18.0 MW | Withdrawn / abandoned |
| Hydro project 51, Teton County Hydro |
15.0 MW | Withdrawn / abandoned |
| Gas project GI-0102a, Valley County Gas |
14.0 MW | Withdrawn / abandoned |
| Hydro project 43, Lake County Hydro |
14.0 MW | Withdrawn / abandoned |
| Hydro project 81, Cascade County Hydro |
12.0 MW | Withdrawn / abandoned |
| Onshore wind project 161, Liberty County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 86, Glacier County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 132, Teton County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 58, Madison County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 120, Judith Basin County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 122, Judith Basin County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 149, Wheatland County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Hydro project 169, Big Horn County Hydro |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 85, Wheatland County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 92, Cascade County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 137, Stillwater County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 121, Judith Basin County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 114, Wheatland County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 125, Judith Basin County Onshore wind |
10.0 MW | Withdrawn / abandoned |
| Gas project 130, Yellowstone County Gas |
10.0 MW | Withdrawn / abandoned |
| Onshore wind project 142, Wheatland County Onshore wind |
9.9 MW | Withdrawn / abandoned |
| Onshore wind project 143, Wheatland County Onshore wind |
9.9 MW | Withdrawn / abandoned |
| Onshore wind project 141, Wheatland County Onshore wind |
9.9 MW | Withdrawn / abandoned |
| Onshore wind project 144, Wheatland County Onshore wind |
9.9 MW | Withdrawn / abandoned |
| Hydro project 167, Broadwater County Hydro |
9.8 MW | Withdrawn / abandoned |
| Hydro project 605, Big Horn County Hydro |
9.2 MW | Withdrawn / abandoned |
| Onshore wind project 323, Meagher County Onshore wind |
9.0 MW | Withdrawn / abandoned |
| Hydro project C4-094, Bighorn County Hydro |
8.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)379 · 30.8 GW
- SPP (Southwest Power Pool)12 · 2,303 MW
- MISO (Midcontinent)4 · 382 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)