United States βΊ Grid βΊ Interconnection queues βΊ Montana
ONSHORE WIND Β· WESTOnshore wind project 86, Glacier County
Onshore wind project 86, Glacier County is a 10.0 MW onshore wind request withdrawn in the West interconnection queue, in Glacier County, Montana, connecting to NorthWestern Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 86
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Near Glacier
- Location
- Glacier County, Montana
- Technology
- Wind: 10.0 MW
- Total requested
- 10.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study System Impact Re-Study
- Queue status
- Withdrawn
- Entered queue
- 14 April 2008
- Proposed online date
- December 2008
Location
Marker shows the centre of Glacier County; the queue data does not give exact sites.
Other requests in Glacier County
- Onshore wind project 78, Glacier CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project 87, Glacier CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project 73, Glacier CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project 95, Glacier CountyOnshore wind Β· 5.0 MW Β· built
- Onshore wind project 56, Glacier CountyOnshore wind Β· 110 MW Β· withdrawn
- Onshore wind project 17, Glacier CountyOnshore wind Β· 75.0 MW Β· withdrawn
- Onshore wind project 140, Glacier CountyOnshore wind Β· 45.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem