United States › Grid › Interconnection queues › Maryland

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Maryland — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown40746.5 GW
Active in queue5,942 MW57 requests
Agreement signed1,462 MW14 requests
Withdrawn40746.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

407 requests · page 5 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AB1-162, Queen Anne's County
Solar
16.7 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2015target 2017
Downsville Solar
Solar
16.0 MWWithdrawn / abandoned Washington, MDPJM Aug 2020target 2022
Route 632 Washington Solar Facility
Solar
16.0 MWWithdrawn / abandoned Washington, MDPJM Apr 2015target 2017
Other project Y3-110, Wicomico County
Other
15.7 MWWithdrawn / abandoned Wicomico, MDPJM Apr 2013target 2016
Solar project AH1-253, Queen Anne's County
Solar
15.5 MWWithdrawn / abandoned Queen Anne's, MDPJM Sep 2021target 2024
Solar project AG2-295, Queen Anne's County
Solar
15.5 MWWithdrawn / abandoned Queen Anne's, MDPJM Mar 2021target 2023
Hydro project AA2-020, Garrett County
Hydro
15.0 MWWithdrawn / abandoned Garrett, MDPJM Dec 2014target 2017
Hydro project AC2-021, Garrett County
Hydro
15.0 MWWithdrawn / abandoned Garrett, MDPJM Jan 2017target 2019
Solar project Y1-087, Wicomico County
Solar
15.0 MWWithdrawn / abandoned Wicomico, MDPJM Apr 2012target 2016
Crockett Solar Project
Solar
15.0 MWWithdrawn / abandoned Talbot, MDPJM Apr 2019target 2026
Solar project AA1-141, Worcester County
Solar
15.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2014target 2016
Solar project AB2-167, Worcester County
Solar
14.0 MWWithdrawn / abandoned Worcester, MDPJM Apr 2016target 2017
Hydro project AG2-505, Garrett County
Hydro · Fairlawn Hydroelectric Company, LLC
14.0 MWWithdrawn / abandoned Garrett, MDPJM Mar 2025target 2023
Solar project AG1-459, Washington County
Solar
14.0 MWWithdrawn / abandoned Washington, MDPJM Sep 2020target 2023
Solar project Z1-076, Worcester County
Solar
14.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2018
Other project AD2-103, Baltimore County
Other
14.0 MWWithdrawn / abandoned Baltimore, MDPJM Mar 2018target 2019
Hydro project U4-007, Garrett County
Hydro
14.0 MWWithdrawn / abandoned Garrett, MDPJM Nov 2008target 2013
Solar project AA2-036, Dorchester County
Solar
14.0 MWWithdrawn / abandoned Dorchester, MDPJM Jan 2015target 2015
Solar project AB2-144, Frederick County
Solar
13.8 MWWithdrawn / abandoned Frederick, MDPJM Apr 2016target 2017
Sand Flat Road Solar Project
Solar
13.8 MWWithdrawn / abandoned Garrett, MDPJM Apr 2019target 2023
Solar project AB2-142, Caroline County
Solar
13.4 MWWithdrawn / abandoned Caroline, MDPJM Apr 2016target 2018
Gas project AF2-155, Prince George's County
Gas
13.0 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2020target 2021
Solar project W3-071, Worcester County
Solar
12.5 MWWithdrawn / abandoned Worcester, MDPJM Sep 2010target 2012
Solar project Y3-057, Charles County
Solar
12.0 MWWithdrawn / abandoned Charles, MDPJM Mar 2013target 2014
Perennial Solar Project
Solar
12.0 MWWithdrawn / abandoned Washington, MDPJM Oct 2014target 2024
Solar project X3-074, Kent County
Solar
11.9 MWWithdrawn / abandoned Kent, MDPJM Oct 2011target 2013
Other project AC2-189, Somerset County
Other
11.6 MWWithdrawn / abandoned Somerset, MDPJM Mar 2017target 2018
Battery storage project AF1-269, Dorchester County
Battery storage
11.0 MWWithdrawn / abandoned Dorchester, MDPJM Sep 2019target 2022
Solar project AG2-092, Dorchester County
Solar · Richfield Solar Energy LLC
11.0 MWWithdrawn / abandoned Dorchester, MDPJM Jan 2021target 2021
CleanLight Power Solar Facility
Solar
10.9 MWWithdrawn / abandoned Garrett, MDPJM Aug 2015target 2019
Solar project W4-020, Montgomery County
Solar
10.1 MWWithdrawn / abandoned Montgomery, MDPJM Nov 2010target 2011
Solar project AA1-122, Washington County
Solar
10.0 MWWithdrawn / abandoned Washington, MDPJM Oct 2014target 2016
Solar project Z1-125, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Solar project AA2-085, Washington County
Solar
10.0 MWWithdrawn / abandoned Washington, MDPJM Mar 2015target 2016
Solar project AA2-150, Talbot County
Solar
10.0 MWWithdrawn / abandoned Talbot, MDPJM Apr 2015target 2016
Solar project Z1-117, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project Z1-123, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Solar project Z1-118, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project X1-025, St. Mary's County
Solar
10.0 MWWithdrawn / abandoned St. Mary's, MDPJM Feb 2011target 2012
Battery storage project AF2-410, Dorchester County
Battery storage
10.0 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2020target 2021
Webb Solar
Solar
10.0 MWWithdrawn / abandoned Garrett, MDPJM Feb 2020target 2022
Solar project Z1-121, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016
Solar project AA2-144, Dorchester County
Solar
10.0 MWWithdrawn / abandoned Dorchester, MDPJM Apr 2015target 2016
Solar project X1-022, St. Mary's County
Solar
10.0 MWWithdrawn / abandoned St. Mary's, MDPJM Feb 2011target 2012
Costen Solar Energy Center
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Apr 2016target 2019
Solar project Z1-124, Worcester County
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2013target 2016
Solar project W4-076, Prince George's County
Solar
10.0 MWWithdrawn / abandoned Prince George's, MDPJM Jan 2011target 2011
Solar project Z2-096, Kent County
Solar
10.0 MWWithdrawn / abandoned Kent, MDPJM Apr 2014target 2016
Worcester Solar Facility
Solar
10.0 MWWithdrawn / abandoned Worcester, MDPJM Oct 2010target 2017
Solar project Z1-120, Somerset County
Solar
10.0 MWWithdrawn / abandoned Somerset, MDPJM Oct 2013target 2016

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)