United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

SOLAR Β· PJM

Solar project Y3-057, Charles County

Solar project Y3-057, Charles County is a 12.0 MW solar request withdrawn in the PJM interconnection queue, in Charles County, Maryland, connecting to PEPCO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2013 (completed)
  2. Withdrawn / abandonedApr 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Y3-057
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Forest Park
Location
Charles County, Maryland
Technology
Solar: 12.0 MW
Total requested
12.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
13 March 2013
Proposed online date
September 2014
Withdrawn
April 2013

Location

Marker shows the centre of Charles County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Charles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem