United States βΊ Grid βΊ Interconnection queues βΊ Maryland
SOLAR Β· PJMSolar project Y3-057, Charles County
Solar project Y3-057, Charles County is a 12.0 MW solar request withdrawn in the PJM interconnection queue, in Charles County, Maryland, connecting to PEPCO.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2013 (completed)
- Withdrawn / abandonedApr 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Y3-057
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Connection point (POI)
- Forest Park
- Location
- Charles County, Maryland
- Technology
- Solar: 12.0 MW
- Total requested
- 12.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 13 March 2013
- Proposed online date
- September 2014
- Withdrawn
- April 2013
Location
Marker shows the centre of Charles County; the queue data does not give exact sites.
Other requests in Charles County
- Battery storage project AI2-457, Charles CountyBattery storage Β· 1,122 MW Β· in study
- Battery storage project AH2-265, Charles CountyBattery storage Β· 200 MW Β· in study
- Solar project AG2-618, Charles CountySolar Β· 110 MW Β· in study
- Solar project AH2-266, Charles CountySolar Β· 25.0 MW Β· in study
- Charles County Solar ISolar Β· 20.0 MW Β· suspended
- Charles County Solar IISolar Β· 20.0 MW Β· suspended
- St. Charles Combined Cycle FacilityGas Β· 725 MW Β· built
- Morgantown Units 1 & 2Gas Β· 80.0 MW Β· built
- CPV MarylandGas Β· 75.0 MW Β· built
- St. Charles Combined Cycle FacilityGas Β· 60.0 MW Β· built
- Ripley SolarSolar Β· 27.5 MW Β· built
- Other project AF2-152, Charles CountyOther Β· 2.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem