United States › Grid › Interconnection queues › Arizona

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Arizona — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown699198.8 GW
Active in queue108.6 GW281 requests
Agreement signed9,849 MW17 requests
Withdrawn699198.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

699 requests · page 5 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Brenda Renewable Energy Complex
Solar
358 MWWithdrawn / abandoned La Paz, AZCAISO Apr 2021target 2025
Gas project Q03, Pinal County
Gas
352 MWWithdrawn / abandoned Pinal, AZWest Sep 2008target 2012
Solar project Q54, Pinal County
Solar
352 MWWithdrawn / abandoned Pinal, AZWest Oct 2008target 2012
Solar + storage project Q501, Pinal County
Solar + storage
350 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2027
Gas project Q39, Maricopa County
Gas
350 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Battery storage project Q530, Maricopa County
Battery storage
350 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2026
Solar + storage project Q342, Navajo County
Solar + storage
345 MWWithdrawn / abandoned Navajo, AZWest Mar 2020target 2023
Other project Q541, Maricopa County
Other
330 MWWithdrawn / abandoned Maricopa, AZWest Sep 2023target 2026
Battery storage project Q503, Maricopa County
Battery storage
321 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Battery storage project 99, Pinal County
Battery storage
319 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2025
Coal project Q5, Navajo County
Coal
316 MWWithdrawn / abandoned Navajo, AZWest Jan 2005target 2006
Harquahala Sun
Solar + storage
313 MWWithdrawn / abandoned Maricopa, AZCAISO May 2017target 2020
Century Solar
Solar
310 MWWithdrawn / abandoned Maricopa, AZCAISO May 2016target 2021
Fort Mojave Solar
Solar
310 MWWithdrawn / abandoned Mojave, AZCAISO Feb 2010target 2019
Battery storage project Q535, Maricopa County
Battery storage
310 MWWithdrawn / abandoned Maricopa, AZWest Aug 2023target 2028
Gas project Q05, Pinal County
Gas
303 MWWithdrawn / abandoned Pinal, AZWest Aug 2008target 2015
Other project Q197, Coconino County
Other
302 MWWithdrawn / abandoned Coconino, AZWest May 2011target 2013
Solar + storage project Q2410, Pinal County
Solar + storage
301 MWWithdrawn / abandoned Pinal, AZWest Feb 2024target 2027
Solar + storage project Q513, Yuma County
Solar + storage
300 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2026
Hyder Valley Solar Energy
Solar
300 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2013target 2018
Solar + storage project Q516, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2027
Onshore wind project 168, Cochise County
Onshore wind
300 MWWithdrawn / abandoned Cochise, AZWest Apr 2024target 2030
Solar project Q69, La Paz County
Solar
300 MWWithdrawn / abandoned La Paz, AZWest Jun 2009target 2015
Battery storage project Q399, Coconino County
Battery storage
300 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2023
Onshore wind project Q381, Pinal County
Onshore wind
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2024
Solar + storage project Q371, Yuma County
Solar + storage
300 MWWithdrawn / abandoned Yuma, AZWest Mar 2021target 2025
Solar project Q184, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Jan 2011target 2017
Onshore wind project 68, Cochise County
Onshore wind
300 MWWithdrawn / abandoned Cochise, AZWest Apr 2019target 2022
Solar + storage project 64, Pima County
Solar + storage
300 MWWithdrawn / abandoned Pima, AZWest Sep 2018target 2021
Battery storage project Q33, Maricopa County
Battery storage
300 MWWithdrawn / abandoned Maricopa, AZWest Oct 2022target 2025
Solar project Q56, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Dec 2008target 2014
Solar project Q16, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Apr 2011target 2014
Solar project Q233, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Mar 2016target 2021
Solar + storage project Q385, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2025
Solar project Q32, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Aug 2007target 2010
Solar + storage project Q15, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Sep 2020target 2023
Hyder
Solar
300 MWWithdrawn / abandoned Maricopa, AZCAISO May 2008target 2012
Solar + storage project Q248, Maricopa County
Solar + storage
300 MWWithdrawn / abandoned Maricopa, AZWest Sep 2016target 2021
Onshore wind project Q525, Mohave County
Onshore wind
300 MWWithdrawn / abandoned Mohave, AZWest Mar 2023target 2027
CVH Power I
Solar
300 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2014
Solar project Q06, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Aug 2013target 2021
Solar + storage project Q514, Yuma County
Solar + storage
300 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2026
Onshore wind project 163, Apache County
Onshore wind
300 MWWithdrawn / abandoned Apache, AZWest Sep 2023target 2028
Titan Solar
Gas
300 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2015target 2020
Solar + storage project 150, Cochise County
Solar + storage
300 MWWithdrawn / abandoned Cochise, AZWest Feb 2023target 2027
Onshore wind project Q37, Navajo County
Onshore wind
300 MWWithdrawn / abandoned Navajo, AZWest Dec 2007target 2013
Solar project Q044b., Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest May 2008target 2014
Solar + storage project Q450, Maricopa County
Solar + storage
300 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Gas project Q30, Pinal County
Gas
297 MWWithdrawn / abandoned Pinal, AZWest Apr 2023target 2026
Solar project Q78, Pinal County
Solar
297 MWWithdrawn / abandoned Pinal, AZWest Nov 2009target 2011
Page 5 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)