Withdrawn queue requests in the USA — page 476

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 476 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Fuel Cell
Other
1.8 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2023target 2024
Solar project SGI-PNM-2022-12, Luna County
Solar
1.8 MWWithdrawn / abandoned Luna, NMWest Jan 2022target 2023
Hydro project TCS-49, Fremont County
Hydro
1.8 MWWithdrawn / abandoned Fremont, IDWest Oct 2019
Hydro project 1182, Fremont County
Hydro
1.8 MWWithdrawn / abandoned Fremont, IDWest Oct 2019
Solar project X3-024, Cape May County
Solar
1.8 MWWithdrawn / abandoned Cape May, NJPJM Aug 2011target 2012
Other project 46, Owyhee County
Other
1.8 MWWithdrawn / abandoned Owyhee, IDWest May 2001target 2001
Solar project 939, Umatilla County
Solar
1.8 MWWithdrawn / abandoned Umatilla, ORWest Aug 2017target 2020
Solar project GEN-2017-069, Quay County
Solar
1.8 MWWithdrawn / abandoned Quay, NMSPP May 20172023
Solar project X3-025, Warren County
Solar
1.8 MWWithdrawn / abandoned Warren, NJPJM Aug 2011target 2012
Edgewood
Solar
1.8 MWWithdrawn / abandoned Hancock, OHPJM Aug 2011target 2014
Solar project 902, Linn County
Solar
1.8 MWWithdrawn / abandoned Linn, ORWest Jul 2017target 2020
Onshore wind project 71, Twin Falls County
Onshore wind
1.8 MWWithdrawn / abandoned Twin Falls, IDWest Feb 2002target 2005
Solar project SGI-PNM-2022-21, Luna County
Solar
1.8 MWWithdrawn / abandoned Luna, NMWest Feb 2022target 2023
Capital Group Solar San Antonio
Solar · The Capital Group San Antonio
1.8 MWWithdrawn / abandoned ERCOT Aug 2023target 2023
Hydro project 1158, Douglas County
Hydro
1.8 MWWithdrawn / abandoned Douglas, ORWest Sep 2019target 2022
Solar project X2-095, Cape May County
Solar
1.8 MWWithdrawn / abandoned Cape May, NJPJM Jul 2011target 2012
Solar project C4-014, Multnomah County
Solar
1.8 MWWithdrawn / abandoned Multnomah, ORWest May 2024target 2026
Solar project SGI-PNM-2022-13, San Miguel County
Solar
1.7 MWWithdrawn / abandoned San Miguel, NMWest Jan 2022target 2023
Hydro project 94, Ada County
Hydro
1.7 MWWithdrawn / abandoned Ada, IDWest Aug 2003target 2004
Onshore wind project M18, Lee County
Onshore wind
1.7 MWWithdrawn / abandoned Lee, ILPJM Jun 2004target 2005
Solar project 533, Twin Falls County
Solar
1.7 MWWithdrawn / abandoned Twin Falls, IDWest May 2018
Rathway SP
Solar
1.7 MWWithdrawn / abandoned Middlesex, NJPJM Apr 2010target 2011
Onshore wind project 196-B, Clatsop County
Onshore wind
1.7 MWWithdrawn / abandoned Clatsop, ORWest Feb 2008target 2008
Solar project W3-157, Cumberland County
Solar
1.7 MWWithdrawn / abandoned Cumberland, NJPJM Oct 2010target 2011
Bowman Street 115 kV SS - Augusta Area Study
Solar
1.7 MWWithdrawn / abandoned Kennebec, MEISO-NE Oct 2020target 2023
Onshore wind project N19, Lee County
Onshore wind
1.7 MWWithdrawn / abandoned Lee, ILPJM Dec 2004target 2006
Crystal Spring 646 - EMA ASO
Solar + storage
1.7 MWWithdrawn / abandoned Plymouth, MAISO-NE Jun 2022target 2023
Onshore wind project 164-B, Clatsop County
Onshore wind · Tasco Engineering, Inc.
1.7 MWWithdrawn / abandoned Clatsop, ORWest Oct 2007target 2008
Onshore wind project G372, Pope County
Onshore wind
1.7 MWWithdrawn / abandoned Pope, MNMISO Nov 2003target 2009
Hydro project 831, Klamath County
Hydro
1.7 MWWithdrawn / abandoned Klamath, ORWest Dec 2016target 2017
Solar project AC1-084, Morris County
Solar
1.6 MWWithdrawn / abandoned Morris, NJPJM Sep 2016target 2018
Solar project AH1-638, Atlantic County
Solar
1.6 MWWithdrawn / abandoned Atlantic, NJPJM Sep 2021target 2022
Solar project X1-111, Ocean County
Solar
1.6 MWWithdrawn / abandoned Ocean, NJPJM Apr 2011target 2011
Onshore wind project J1803, Houghton County
Onshore wind
1.6 MWWithdrawn / abandoned Houghton, MIMISO Jun 2020target 2021
Onshore wind project 405, Tooele County
Onshore wind · Tasco Energy, LLC
1.6 MWWithdrawn / abandoned Tooele, UTWest Oct 2011target 2013
Southbridge LFGTE Engine 2
Other
1.6 MWWithdrawn / abandoned Worcester, MAISO-NE Jun 2015target 2018
Other project AA2-185, Prince William County
Other
1.6 MWWithdrawn / abandoned Prince William, VAPJM Apr 2015target 2016
Other project 453, Franklin County
Other · REUT Origination, LLC
1.6 MWWithdrawn / abandoned Franklin, IDWest Jan 2013target 2013
Woodstock 115 kV SS - Roxbury-Rumford-Woodstock Area DG Study
Solar
1.6 MWWithdrawn / abandoned Oxford, MEISO-NE Sep 2023target 2024
Other project 368, Douglas County
Other
1.6 MWWithdrawn / abandoned Douglas, ORWest Jan 2011target 2011
Other project W1-064, Franklin County
Other
1.6 MWWithdrawn / abandoned Franklin, PAPJM Mar 2010target 2011
Hydro project 395, Deschutes County
Hydro
1.6 MWWithdrawn / abandoned Deschutes, ORWest Jul 2011target 2013
Other project V2-027, Northumberland County
Other
1.6 MWWithdrawn / abandoned Northumberland, PAPJM Jul 2009target 2013
Schanzlin Solar Farm
Solar
1.6 MWWithdrawn / abandoned Warren, NJPJM Oct 2010target 2014
Barre Mass Landfill Gas
Other
1.6 MWWithdrawn / abandoned Worcester, MAISO-NE Dec 2007target 2011
West Cranston - NG WRI DG Area Study #2 <5 MW
Solar
1.6 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2022
Solar project AE2-083, Mercer County
Solar
1.6 MWWithdrawn / abandoned Mercer, NJPJM Feb 2019target 2020
Other project Q13, Kankakee County
Other
1.6 MWWithdrawn / abandoned Kankakee, ILPJM Mar 2006target 2007
Other project 386, Polk County
Other
1.6 MWWithdrawn / abandoned Polk, ORWest Apr 2011target 2012
Solar project Y1-014, Kent County
Solar
1.6 MWWithdrawn / abandoned Kent, MDPJM Feb 2012target 2012
Page 476 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)