United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Southeast (non-ISO utilities) — page 44

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,738603.3 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,738 requests · page 44 of 55
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 900727, Clarendon County
Solar
58.5 MWWithdrawn / abandoned Clarendon, SCSoutheast May 2023
Other project 117, Polk County
Other · Masked
58.4 MWWithdrawn / abandoned Polk, FLSoutheast Jun 2012target 2014
Solar project 126036, Union County
Solar
58.0 MWWithdrawn / abandoned Union, SCSoutheast Mar 2020
Solar project 366, Obion County
Solar
58.0 MWWithdrawn / abandoned Obion, TNSoutheast Apr 2019
Solar project 924437, Union County
Solar
58.0 MWWithdrawn / abandoned Union, SCSoutheast Sep 2023
Solar project 568024, Union County
Solar
58.0 MWWithdrawn / abandoned Union, SCSoutheast Jun 2022
Solar project 578, Colbert County
Solar
57.0 MWWithdrawn / abandoned Colbert, ALSoutheast Aug 2023target 2026
Solar project IC-554, Coffee County
Solar
57.0 MWWithdrawn / abandoned Coffee, GASoutheast Dec 2016
Solar project IC-449, Terrell County
Solar
56.0 MWWithdrawn / abandoned Terrell, GASoutheast Mar 2016
Other project 29, Newberry County
Other
55.9 MWWithdrawn / abandoned Newberry, SCSoutheast May 2009target 2012
Solar project 511, Crockett County
Solar
55.0 MWWithdrawn / abandoned Crockett, TNSoutheast Aug 2022target 2025
Other project IC-246, Troup County
Other
55.0 MWWithdrawn / abandoned Troup, GASoutheast Jan 2011
Battery storage project 240, Aiken County
Battery storage
55.0 MWWithdrawn / abandoned Aiken, SCSoutheast Jun 2023target 2027
Solar project 518, Madison County
Solar
55.0 MWWithdrawn / abandoned Madison, TNSoutheast Sep 2022target 2025
Solar project IC-722, Lamar County
Solar
55.0 MWWithdrawn / abandoned Lamar, MSSoutheast Jul 2018
Solar project 962966, Granville County
Solar
55.0 MWWithdrawn / abandoned Granville, NCSoutheast Sep 2024
Solar project 62472, Greenwood County
Solar
55.0 MWWithdrawn / abandoned Greenwood, SCSoutheast Mar 2019
Solar project 920653, Robeson County
Solar
55.0 MWWithdrawn / abandoned Robeson, NCSoutheast Sep 2023
Solar project 63666, Laurens County
Solar
55.0 MWWithdrawn / abandoned Laurens, SCSoutheast Feb 2019
Solar project 16, Polk County
Solar
55.0 MWWithdrawn / abandoned Polk, FLSoutheast Apr 2017target 2018
Solar project IC-715, Gadsden County
Solar
55.0 MWWithdrawn / abandoned Gadsden, FLSoutheast Jun 2018
Solar project 249, Polk County
Solar · Masked
55.0 MWWithdrawn / abandoned Polk, FLSoutheast Feb 2019target 2021
Solar + storage project 545, Dekalb County
Solar + storage
55.0 MWWithdrawn / abandoned Dekalb, TNSoutheast Apr 2023target 2028
Solar project 85, Hillsborough County
Solar
55.0 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2022target 2024
Solar project 91, Polk County
Solar
55.0 MWWithdrawn / abandoned Polk, FLSoutheast Nov 2022target 2025
Solar project 90, Hillsborough County
Solar
55.0 MWWithdrawn / abandoned Hillsborough, FLSoutheast Jun 2022target 2024
Solar project 918573, Vance County
Solar · Masked
55.0 MWWithdrawn / abandoned Vance, NCSoutheast Sep 2023
Solar project 167B, Richland County
Solar
55.0 MWWithdrawn / abandoned Richland, SCSoutheast Oct 2021
Solar project 3, Hillsborough County
Solar
54.6 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2017target 2018
Solar project IC-631, Calhoun County
Solar
54.2 MWWithdrawn / abandoned Calhoun, FLSoutheast Apr 2017
Solar project IC-569, Dale County
Solar
54.0 MWWithdrawn / abandoned Dale, ALSoutheast Dec 2016
Solar + storage project 20230828002, Orangeburg County
Solar + storage
54.0 MWWithdrawn / abandoned Orangeburg, SCSoutheast target 2026
Solar + storage project 20180508001, Fairfield County
Solar + storage
54.0 MWWithdrawn / abandoned Fairfield, SCSoutheast target 2019
Solar project 468, Franklin County
Solar
53.0 MWWithdrawn / abandoned Franklin, TNSoutheast Feb 2021
Solar project 18
Solar
52.8 MWWithdrawn / abandoned FLSoutheast May 2016target 2020
Solar project 22082, Newberry County
Solar
52.1 MWWithdrawn / abandoned Newberry, SCSoutheast Aug 2018
Solar project IC-471, Decatur County
Solar
52.0 MWWithdrawn / abandoned Decatur, GASoutheast Jul 2016
Solar project IC-551, Tattnall County
Solar
52.0 MWWithdrawn / abandoned Tattnall, GASoutheast Dec 2016
Solar project 343, Chickasaw County
Solar
52.0 MWWithdrawn / abandoned Chickasaw, MSSoutheast Apr 2018
Solar project IC-588, Lowndes County
Solar
52.0 MWWithdrawn / abandoned Lowndes, GASoutheast Jan 2017
Solar project IC-713, Macon County
Solar
52.0 MWWithdrawn / abandoned Macon, GASoutheast Jun 2018
Solar project 569234, Johnston County
Solar
51.7 MWWithdrawn / abandoned Johnston, NCSoutheast Jun 2022
Solar project IC-492, Houston County
Solar
50.5 MWWithdrawn / abandoned Houston, GASoutheast Sep 2016
Battery storage project 428, Oktibbeha County
Battery storage
50.0 MWWithdrawn / abandoned Oktibbeha, MSSoutheast Apr 2020
Solar project 184, Orangeburg County
Solar
50.0 MWWithdrawn / abandoned Orangeburg, SCSoutheast Jun 2023target 2025
Solar project 26829, Johnston County
Solar · Masked
50.0 MWWithdrawn / abandoned Johnston, NCSoutheast Dec 2018
Solar project 20240829015, Barnwell County
Solar
50.0 MWWithdrawn / abandoned Barnwell, SCSoutheast target 2027
Solar project 562906, Kershaw County
Solar
50.0 MWWithdrawn / abandoned Kershaw, SCSoutheast Jun 2022
Solar project IC-657, Bay County
Solar
50.0 MWWithdrawn / abandoned Bay, FLSoutheast Dec 2017
Solar project 159, Berkeley County
Solar
50.0 MWWithdrawn / abandoned Berkeley, SCSoutheast Jan 2021target 2022
Page 44 of 55

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)