United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 412

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 412 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project 435, Lake County
Battery storage
17.0 MWWithdrawn / abandoned Lake, TNSoutheast Jun 2020
Other project 156, Anderson County
Other
17.0 MWWithdrawn / abandoned Anderson, TNSoutheast Apr 2001
Gas project PIS059, Salt Lake County
Gas · PacifiCorp
17.0 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2026
Coal project 97, Hernando County
Coal · Masked
17.0 MWWithdrawn / abandoned Hernando, FLSoutheast Feb 2009target 2009
Solar project AG2-520, Prince George's County
Solar
17.0 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2021target 2024
Gas project C4-060, Salt Lake County
Gas · PacifiCorp
17.0 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2026
Solar project J3507, Montgomery County
Solar
17.0 MWWithdrawn / abandoned Montgomery, ILMISO Apr 2024target 2027
Solar project AH1-070, Ashland County
Solar · JR ME LLC
17.0 MWWithdrawn / abandoned Ashland, OHPJM Mar 2025target 2023
Battery storage project AA2-064, Sussex County
Battery storage
17.0 MWWithdrawn / abandoned Sussex, NJPJM Feb 2015target 2015
Stewartsville II Solar Farm
Solar
17.0 MWWithdrawn / abandoned Warren, NJPJM Nov 2010target 2014
Route 519 Solar Farm
Solar
17.0 MWWithdrawn / abandoned Hunterdon, NJPJM Oct 2010target 2014
Solar project Q294, Yavapai County
Solar
17.0 MWWithdrawn / abandoned Yavapai, AZWest Nov 2018target 2021
Swayles Solar Farm
Solar
17.0 MWWithdrawn / abandoned Middlesex, NJPJM Oct 2010target 2014
Gas project J1141, Manistee County
Gas
17.0 MWWithdrawn / abandoned Manistee, MIMISO Mar 2018target 2019
Solar project Q345, Maricopa County
Solar
17.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2020target 2021
Hampton Township Solar Farm
Solar
17.0 MWWithdrawn / abandoned Sussex, NJPJM Oct 2010target 2014
Solar
Solar
17.0 MWWithdrawn / abandoned Oxford, MEISO-NE Jan 2020target 2024
Seven Bridges Solar
Solar
17.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2019target 2025
Solar project 349, Pontotoc County
Solar
17.0 MWWithdrawn / abandoned Pontotoc, MSSoutheast May 2018
Sherbino II BESS SLF (Placeholder)
Other · Phoenix Battery Storage, LLC
17.0 MWWithdrawn / abandoned Pecos, TXERCOT target 2025
Solar project IC-530, Pickens County
Solar
17.0 MWWithdrawn / abandoned Pickens, ALSoutheast Nov 2016
Perotti Solar Farm
Solar
17.0 MWWithdrawn / abandoned Hunterdon, NJPJM Jul 2010target 2014
Solar project W2-089, Burlington County
Solar
17.0 MWWithdrawn / abandoned Burlington, NJPJM Jul 2010target 2012
Onshore wind project G613, Redwood County
Onshore wind
17.0 MWWithdrawn / abandoned Redwood, MNMISO Mar 2006target 2008
Flemington Solar Farm
Solar
17.0 MWWithdrawn / abandoned Hunterdon, NJPJM Apr 2011target 2012
Battery storage project 467, Lawrence County
Battery storage
17.0 MWWithdrawn / abandoned Lawrence, ALSoutheast Feb 2021
Mount Olive Solar Farm
Solar
17.0 MWWithdrawn / abandoned Morris, NJPJM Apr 2011target 2015
Polizzi Solar Farm
Solar
17.0 MWWithdrawn / abandoned Ocean, NJPJM Oct 2010target 2014
Solar project AD1-077, Greene County
Solar
17.0 MWWithdrawn / abandoned Greene, VAPJM Sep 2017target 2019
Battery storage project AG1-426, Buckingham County
Battery storage · Riverstone Solar, LLC
17.0 MWWithdrawn / abandoned Buckingham, VAPJM Sep 2020target 2023
W. Charlton substation - NG Western MA Area Cluster Study
Solar
17.0 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2022
NextEra Energy Resources
Onshore wind · NextEra Energy Resources, LLC
17.0 MWWithdrawn / abandoned Umatilla, ORWest Feb 2004target 2005
Syncarpha Ty Solar Farm
Solar
17.0 MWWithdrawn / abandoned Sussex, NJPJM Oct 2010target 2014
Freehold Solar Farm
Solar
17.0 MWWithdrawn / abandoned Monmouth, NJPJM Jul 2010target 2014
EE 2024 SEMA/Cape ASO Group Study
Solar + storage
16.9 MWWithdrawn / abandoned Plymouth, MAISO-NE May 2024target 2026
Gas project E15, Luzerne County
Gas
16.9 MWWithdrawn / abandoned Luzerne, PAPJM Nov 2000
Onshore wind project H04, Luzerne County
Onshore wind
16.9 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2001target 2002
Solar project AC1-163, Hertford County
Solar
16.9 MWWithdrawn / abandoned Hertford, NCPJM Oct 2016target 2019
Gas project E11, Luzerne County
Gas
16.9 MWWithdrawn / abandoned Luzerne, PAPJM Oct 2000
Emsworth Main Channel Hydroelectric Project 2
Hydro
16.8 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2020target 2025
Other project GEN-2008-070S, Tulsa County
Other
16.8 MWWithdrawn / abandoned Tulsa, OKSPP Jul 2008
Solar project X1-106, Sussex County
Solar
16.8 MWWithdrawn / abandoned Sussex, NJPJM Apr 2011target 2012
Delight Farm
Solar · AES DE DEVCO NC LLC
16.8 MWWithdrawn / abandoned Cayuga, NYNYISO Jul 2020
Solar project AF1-004, Charles County
Solar
16.8 MWWithdrawn / abandoned Charles, MDPJM Apr 2019target 2021
Centerville Pike Solar
Solar
16.7 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Mar 2017target 2021
Solar project J507, Pulaski County
Solar
16.7 MWWithdrawn / abandoned Pulaski, ARMISO Nov 2015target 2016
Solar project AH1-173, Tazewell County
Solar
16.7 MWWithdrawn / abandoned Tazewell, VAPJM Aug 2021target 2022
Solar project AH1-274, Gloucester County
Solar · Vineland Newfield Solar Farm, LLC
16.7 MWWithdrawn / abandoned Gloucester, NJPJM Mar 2025target 2022
Solar project AB1-162, Queen Anne's County
Solar
16.7 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2015target 2017
Solar project W3-084, Hunterdon County
Solar
16.6 MWWithdrawn / abandoned Hunterdon, NJPJM Oct 2010target 2011
Page 412 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)