πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project G613, Redwood County

Onshore wind project G613, Redwood County is a 17.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Redwood County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2006 (completed)
  2. Withdrawn / abandonedMar 2008 (project stopped here)
  3. ConsentedMar 2008 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G613
Grid region
MISO (Midcontinent)
Connection point (POI)
Redwood Electric Substation 6 69 kV
Location
Redwood County, Minnesota
Technology
Wind: 17.0 MW
Total requested
17.0 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
24 March 2006
Agreement signed
24 March 2008
Proposed online date
August 2008
Withdrawn
March 2008

Location

Marker shows the centre of Redwood County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Redwood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem