United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 4 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Other project 152, Muhlenberg County
Other
1,500 MWWithdrawn / abandoned Muhlenberg, KYSoutheast Mar 2001
Searchlight 1
Onshore wind
1,500 MWWithdrawn / abandoned Clark, NVCAISO Aug 2006target 2011
Onshore wind project GI-0611, Hand County
Onshore wind
1,500 MWWithdrawn / abandoned Hand, SDWest Aug 2006target 2009
Onshore wind project G896, Scott County
Onshore wind
1,500 MWWithdrawn / abandoned Scott, MNMISO Oct 2007target 2010
Onshore wind project G704, Hand County
Onshore wind
1,500 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2007
Onshore wind project GI-0609, Buffalo County
Onshore wind
1,500 MWWithdrawn / abandoned Buffalo, SDWest Jul 2006target 2009
Solar + storage project G0852, Wasco County
Solar + storage
1,500 MWWithdrawn / abandoned Wasco, ORWest Mar 2023target 2027
Onshore wind project G884, Roberts County
Onshore wind
1,500 MWWithdrawn / abandoned Roberts, SDMISO Oct 2007target 2011
Onshore wind project X1-020, Cass County
Onshore wind
1,500 MWWithdrawn / abandoned Cass, INPJM Feb 2011target 2018
Offshore wind project AH2-240, Monmouth County
Offshore wind
1,493 MWWithdrawn / abandoned Monmouth, NJPJM Mar 2022target 2027
Nuclear project 234, Jackson County
Nuclear
1,480 MWWithdrawn / abandoned Jackson, ALSoutheast Apr 2012
Gas project AH1-690, Lucas County
Gas · CPV Oregon, LLC
1,475 MWWithdrawn / abandoned Lucas, OHPJM Apr 2025
Gas project AB1-003, Indiana County
Gas
1,474 MWWithdrawn / abandoned Indiana, PAPJM May 2015target 2019
Bravo Wind
Offshore wind
1,465 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2034
Lighthouse Wind
Offshore wind
1,456 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2027
Gas project AH1-689, Columbia County
Gas · Invitium Energy, LLC
1,450 MWWithdrawn / abandoned Columbia, PAPJM target 2030
Other project 165, Maury County
Other
1,450 MWWithdrawn / abandoned Maury, TNSoutheast Jun 2001
Other project 168, Jackson County
Other
1,450 MWWithdrawn / abandoned Jackson, ALSoutheast Jun 2001
Other project 164, Wilson County
Other
1,450 MWWithdrawn / abandoned Wilson, TNSoutheast Jun 2001
Other project 169, Robertson County
Other
1,450 MWWithdrawn / abandoned Robertson, TNSoutheast Jun 2001
Gas project AH1-688, Columbia County
Gas · Invitium Energy, LLC
1,450 MWWithdrawn / abandoned Columbia, PAPJM target 2030
EI Empire ESS II
Wind + storage · Empire Offshore Wind LLC
1,440 MWWithdrawn / abandoned Nassau, NYNYISO May 2021
Icarus Solar
Solar + storage
1,435 MWWithdrawn / abandoned Mohave, AZCAISO Apr 2023target 2032
Other project G265, Campbell County
Other
1,420 MWWithdrawn / abandoned Campbell, WYMISO Nov 2002target 2004
Offshore wind project AH1-384, Sussex County
Offshore wind
1,410 MWWithdrawn / abandoned Sussex, DEPJM Sep 2021target 2027
Eagle Mountain Pump Storage #4
Battery storage
1,408 MWWithdrawn / abandoned Riverside, CACAISO Apr 2015target 2022
Iron Hills Pumped Storage
Battery storage
1,407 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2025
Vineyard Wind I
Offshore wind · OCS-A 0522, LLC
1,403 MWWithdrawn / abandoned Nassau, NYNYISO Apr 2020
Vineyard Wind II
Offshore wind · OCS-A 0522, LLC
1,403 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2020
Atlantic Shores Offshore Wind Project 5
Offshore wind · ATLANTIC SHORES OFFSHORE WIND BIGHT LLC
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Atlantic Shores Offshore Wind Project 3
Offshore wind · ATLANTIC SHORES OFFSHORE WIND LLC
1,400 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
Solar + storage project LGE-GIS-2022-005, Clarke County
Solar + storage
1,400 MWWithdrawn / abandoned Clarke, INSoutheast Jul 2022target 2029
NY Wind - Pilgrim CSR
Wind + storage · Bay State Wind
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2023
NY Wind - Mott Haven CSR
Wind + storage · Bay State Wind
1,400 MWWithdrawn / abandoned Bronx, NYNYISO Jan 2023
Atlantic Shores Offshore Wind Project 4
Offshore wind · Atlantic Shores Offshore Wind Bight LLC
1,400 MWWithdrawn / abandoned Kings, NYNYISO Aug 2024
Eagle Mountain Pump Storage #3
Hydro
1,400 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2017
Eagle Mountain Pump Storage #2
Hydro
1,400 MWWithdrawn / abandoned Riverside, CACAISO Feb 2010target 2016
Ses Solar Six
Solar
1,400 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2006target 2013
Onshore wind project AH2-285, Middlesex County
Onshore wind
1,400 MWWithdrawn / abandoned Middlesex, NJPJM Mar 2022target 2029
Gas project 110, Pasco County
Gas · Duke Energy Florida, LLC
1,400 MWWithdrawn / abandoned Pasco, FLSoutheast Jul 2011target 2018
NY Wind - Pilgrim Uprate
Offshore wind · Bay State Wind
1,400 MWWithdrawn / abandoned Suffolk, NYNYISO Nov 2022
Gas project 109, Pasco County
Gas · Duke Energy Florida, LLC
1,400 MWWithdrawn / abandoned Pasco, FLSoutheast Jul 2011target 2016
Southern Sierra PSP
Other
1,392 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Helms PSP Uprate
Battery storage
1,392 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Bluepoint Wind 4
Offshore wind · Bluepoint Wind LLC
1,382 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2023
Gas project AA2-142, Somerset County
Gas
1,377 MWWithdrawn / abandoned Somerset, NJPJM Apr 2015target 2021
Nuclear project J372, Rock Island County
Nuclear
1,373 MWWithdrawn / abandoned Rock Island, ILMISO Jun 2014target 2019
Community OSW Brooklyn CEH 3
Onshore wind · Community Offshore Wind, LLC
1,365 MWWithdrawn / abandoned Kings, NYNYISO Nov 2023
Salmon Falls Wind
Wind + storage
1,356 MWWithdrawn / abandoned Twin Falls, IDCAISO Apr 2021target 2026
Vineyard Mid-Atlantic 1
Offshore wind · Vineyard Mid-Atlantic
1,350 MWWithdrawn / abandoned Kings, NYNYISO Aug 2022
Page 4 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)