πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in the USA (2012 requests) β€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown17617.9 GW
Active in queue1,925 MW19 requests
Agreement signed152 MW7 requests
Withdrawn39770.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

176 requests Β· page 4 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Warren County Landfill
Solar
3.8 MWOperating Warren, NJPJM Jun 20122014
Hydro project J241, Florence County
Hydro
3.7 MWOperating Florence, WIMISO Apr 20122016
Hydro project GEN-2011-056A, Dawson County
Hydro
3.6 MWOperating Dawson, NESPP Mar 20122012
Roundtop Energy Project
Gas
3.5 MWOperating Susquehanna, PAPJM Aug 20122015
Constellation Solar Maryland II, LLC Solar Facility
Solar
3.4 MWOperating Dorchester, MDPJM Apr 20122015
Solar project Q213, Yuma County
Solar
3.0 MWOperating Yuma, AZWest May 2012target 2012
City of Walla Walla Mill Creek Hydroelectric
Hydro
3.0 MWOperating Walla Walla, WAWest Jun 2012target 2013
G0480 Port of Tillamook Bay Gas Digester Project
Other
2.0 MWOperating Tillamook, ORWest Dec 2012target 2013
Gas project GEN-2012-044, Crawford County
Gas
2.0 MWOperating Crawford, KSSPP Dec 20122013
Geothermal project 414, Klamath County
Geothermal Β· Oregon Institute of Technology
1.8 MWOperating Klamath, ORWest Mar 2012target 2014
Solar project 438, Tooele County
Solar Β· Tooele Army Depot
1.8 MWOperating Tooele, UTWest Aug 2012target 2016
Onshore wind project 439, Tooele County
Onshore wind Β· Tooele Army Depot
1.6 MWOperating Tooele, UTWest Aug 2012target 2016
Whitefish In-Line Hydroelectric Project
Hydro
1.0 MWOperating Flathead, MTWest Jan 2012target 2012
Barbadoes Energy Storage Unit
Battery storage
1.0 MWOperating Montgomery, PAPJM Apr 20122013
Other project G0470, Yamhill County
Other
1.0 MWOperating Yamhill, ORWest Mar 2012target 2012
Reeve's Station South
Solar
1.0 MWOperating Burlington, NJPJM Apr 20122013
Eagle Creek Hydro
Hydro Β· Eagle Creek Hydro, LLC
0.8 MWOperating Sullivan, NYNYISO Mar 20122014
Eagle Creek Hydro
Hydro Β· Eagle Creek Hydro, LLC
0.8 MWOperating NYNYISO Mar 2012
Gas project GI-1203, Williams County
Gas Β· Blaise Energy
0.8 MWOperating Williams, NDWest Feb 2012target 2012
Hydro project 437, Franklin County
Hydro Β· Consolidated Irrigation Company
0.5 MWOperating Franklin, IDWest Sep 2012target 2015
Bayview
Other
0.5 MWOperating Northampton, VAPJM Nov 20122013
Mechanicsville Hydro Increase
Hydro
0.3 MWOperating Windham, CTISO-NE Oct 2012target 2013
Hydro project 413, Jefferson County
Hydro Β· Apple, Inc
0.3 MWOperating Jefferson, ORWest Feb 2012target 2015
Onshore wind project GI-1215, Phillips County
Onshore wind Β· MT DEQ (Landusky)
0.2 MWOperating Phillips, MTWest Oct 2012target 2012
Pisgah Mountain Increase (see Q349)
Onshore wind
0.1 MWOperating Penobscot, MEISO-NE Dec 2012target 2016
Hydro project 400, Gooding County
Hydro
0.0 MWOperating Gooding, IDWest Dec 2012target 2012
Page 4 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)