United States › Grid › Interconnection queues › Florida
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Florida — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 329, Hamilton County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 256, Highlands County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 291, Wakulla County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 95A, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 257, Highlands County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 28 Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 331, Hamilton County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 262, Gilchrist County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 603, Union County Solar · Third Party |
74.9 MW | Withdrawn / abandoned |
| Solar project 138B, Bradford County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 65, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 213, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 218C, Gilchrist County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 261, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 268, Alachua County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 223, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 601, Union County Solar · Third Party |
74.9 MW | Withdrawn / abandoned |
| Solar project 555, Bradford County Solar · Third Party |
74.9 MW | Withdrawn / abandoned |
| Solar project 260, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 556, Bradford County Solar · Third Party |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-658, Jackson County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 138A, Hamilton County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 96B, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 289, Alachua County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 78, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 275, Polk County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 215, Alachua County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 138C, Highlands County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-599, Calhoun County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 224, Suwannee County Solar · Patchwork Solar, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-654, Okaloosa County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project FC100005, Highlands County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 27 Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-558, Jackson County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 216, Alachua County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 175, Highlands County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 79, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 300, Gilchrist County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 313, Levy County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 232C, Marion County Solar · Leeward Renewable Energy, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 339, Suwannee County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 220, Madison County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 219, Madison County Solar · Marsh Solar, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 92, Hillsborough County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project FC100011, Alachua County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project FC100016, Hamilton County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 153, Columbia County Solar · Penholoway Solar, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 93A, Polk County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 294, Gilchrist County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 267, Alachua County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)