United States › Grid › Interconnection queues › Arizona
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Arizona — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project Q531, Maricopa County Solar + storage |
441 MW | Withdrawn / abandoned |
| Solar project Q04, Maricopa County Solar |
440 MW | Withdrawn / abandoned |
| Solar project Q03, Maricopa County Solar |
440 MW | Withdrawn / abandoned |
| Solar + storage project Q2416, Maricopa County Solar + storage |
420 MW | Withdrawn / abandoned |
| Solar + storage project Q343, Maricopa County Solar + storage |
410 MW | Withdrawn / abandoned |
| Winged Dove Storage Battery storage |
409 MW | Withdrawn / abandoned |
| Onshore wind project Q86, Navajo County Onshore wind |
407 MW | Withdrawn / abandoned |
| Battery storage project Q99, Pinal County Battery storage |
406 MW | Withdrawn / abandoned |
| Solar + storage project Q2505, Maricopa County Solar + storage |
405 MW | Withdrawn / abandoned |
| Solar + storage project Q2504, Maricopa County Solar + storage |
405 MW | Withdrawn / abandoned |
| Solar + storage project Q88, Pinal County Solar + storage |
405 MW | Withdrawn / abandoned |
| Coal project Q21, Navajo County Coal |
401 MW | Withdrawn / abandoned |
| Signal Peak Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q515, Yuma County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project Q38, Maricopa County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q17, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q406, Yuma County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar project Q247, Yuma County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q484, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project Q33, Yuma County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q69, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q105, Pinal County Battery storage |
400 MW | Withdrawn / abandoned |
| Coal project Q23, Navajo County Coal |
400 MW | Withdrawn / abandoned |
| Battery storage project Q36, Maricopa County Battery storage |
400 MW | Withdrawn / abandoned |
| Battery storage project 141, Pinal County Battery storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q542, Maricopa County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar project 167, Cochise County Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project 172, Cochise County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project 83, Pima County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q63, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q369, San Juan County Solar + storage |
400 MW | Withdrawn / abandoned |
| Other project 149, Apache County Other |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q02, Maricopa County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q527, Coconino County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project Q366, Coconino County Onshore wind |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q12, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q94, Pinal County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar project Q344 Solar |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q18, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project Q436, Coconino County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q11, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project 97, Apache County Onshore wind |
400 MW | Withdrawn / abandoned |
| Battery storage project Q477, Maricopa County Battery storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q62, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q35, Maricopa County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project Q14, Pinal County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project Q90, Navajo County Onshore wind |
390 MW | Withdrawn / abandoned |
| Solar + storage project Q2517, Pinal County Solar + storage |
373 MW | Withdrawn / abandoned |
| Solar project Q335, Yavapai County Solar |
360 MW | Withdrawn / abandoned |
| Solar + storage project Q545, Yavapai County Solar + storage |
360 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)