πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR Β· WEST

Solar project Q33, Yuma County

Solar project Q33, Yuma County is a 400 MW solar request withdrawn in the West interconnection queue, in Yuma County, Arizona, connecting to Arizona Public Service.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q33
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
North Gila 500 kV Switchyard
Location
Yuma County, Arizona
Technology
Solar: 400 MW
Total requested
400 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
13 August 2007
Proposed online date
January 2015

Location

Marker shows the centre of Yuma County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Yuma County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem