United States › Grid › Interconnection queues › Alabama

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Alabama — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown413104.6 GW
Active in queue14.4 GW91 requests
Agreement signed3,122 MW15 requests
Withdrawn413104.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

413 requests · page 4 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 355, Lawrence County
Solar
150 MWWithdrawn / abandoned Lawrence, ALSoutheast Aug 2018
Solar project 354, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast May 2019
Solar project IC-1278, Escambia County
Solar
150 MWWithdrawn / abandoned Escambia, ALSoutheast Apr 2024
Solar project IC-1065, Escambia County
Solar
150 MWWithdrawn / abandoned Escambia, ALSoutheast Sep 2022
Solar + storage project 25-IC-1352, Henry County
Solar + storage
148 MWWithdrawn / abandoned Henry, ALSoutheast Apr 2025
Solar + storage project IC-1182, Lowndes County
Solar + storage
138 MWWithdrawn / abandoned Lowndes, ALSoutheast Oct 2023target 2027
Solar project IC-1213, Perry County
Solar
136 MWWithdrawn / abandoned Perry, ALSoutheast Dec 2023
Solar project 635, Jackson County
Solar
120 MWWithdrawn / abandoned Jackson, ALSoutheast Jul 2024
Solar project IC-1208, Lowndes County
Solar
120 MWWithdrawn / abandoned Lowndes, ALSoutheast Dec 2023target 2027
Solar project IC-423, Perry County
Solar
118 MWWithdrawn / abandoned Perry, ALSoutheast Dec 2015
Solar + storage project 25-IC-1353, Mobile County
Solar + storage
112 MWWithdrawn / abandoned Mobile, ALSoutheast Apr 2025
Solar + storage project 523, Lake County
Solar + storage
110 MWWithdrawn / abandoned Lake, ALSoutheast Oct 2022target 2026
Other project 235, Cherokee County
Other
101 MWWithdrawn / abandoned Cherokee, ALSoutheast May 2012
Solar project IC-804, Marengo County
Solar
100 MWWithdrawn / abandoned Marengo, ALSoutheast Sep 2019target 2022
Gas project IC-388, Lowndes County
Gas
100 MWWithdrawn / abandoned Lowndes, ALSoutheast Jun 2014
Solar + storage project 437, Lawrence County
Solar + storage
100 MWWithdrawn / abandoned Lawrence, ALSoutheast Jun 2020
Solar + storage project 639, Jackson County
Solar + storage
100 MWWithdrawn / abandoned Jackson, ALSoutheast Aug 2024
Solar project 591, Colbert County
Solar
100 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2023target 2025
Onshore wind project IC-268, Etowah County
Onshore wind
100 MWWithdrawn / abandoned Etowah, ALSoutheast May 2012
Solar project 580, Colbert County
Solar
100 MWWithdrawn / abandoned Colbert, ALSoutheast Jul 2023target 2025
Solar project IC-877, Hale County
Solar
100 MWWithdrawn / abandoned Hale, ALSoutheast Jun 2020
Solar project 617, Caldwell County
Solar
100 MWWithdrawn / abandoned Caldwell, ALSoutheast Jun 2024
Solar + storage project IC-896, Hale County
Solar + storage
100 MWWithdrawn / abandoned Hale, ALSoutheast Jul 2020
Solar project 339, Colbert County
Solar
100 MWWithdrawn / abandoned Colbert, ALSoutheast Feb 2018
Solar project 25-IC-AM, Lowndes County
Solar
100 MWWithdrawn / abandoned Lowndes, ALSoutheast
Solar + storage project IC-841, Washington County
Solar + storage
100 MWWithdrawn / abandoned Washington, ALSoutheast Dec 2019
Solar project 296, Jackson County
Solar
100 MWWithdrawn / abandoned Jackson, ALSoutheast Jun 2016
Solar project IC-846, Hale County
Solar
100 MWWithdrawn / abandoned Hale, ALSoutheast Feb 2020
Solar project IC-1242, Dallas County
Solar
100 MWWithdrawn / abandoned Dallas, ALSoutheast Mar 2024
Solar project 376, Lauderdale County
Solar
100 MWWithdrawn / abandoned Lauderdale, ALSoutheast Jun 2019
Solar + storage project 432, Lauderdale County
Solar + storage
100 MWWithdrawn / abandoned Lauderdale, ALSoutheast May 2020
Solar project IC-487, Baldwin County
Solar
98.0 MWWithdrawn / abandoned Baldwin, ALSoutheast Aug 2016
Solar project IC-428, Elmore County
Solar
94.0 MWWithdrawn / abandoned Elmore, ALSoutheast Jan 2016
Solar project IC-511, Houston County
Solar
90.0 MWWithdrawn / abandoned Houston, ALSoutheast Oct 2016
Onshore wind project IC-267, Cleburne County
Onshore wind
89.0 MWWithdrawn / abandoned Cleburne, ALSoutheast Apr 2012
Onshore wind project IC-323, Cleburne County
Onshore wind
88.4 MWWithdrawn / abandoned Cleburne, ALSoutheast Nov 2013
Solar + storage project IC-854, Wilcox County
Solar + storage
88.0 MWWithdrawn / abandoned Wilcox, ALSoutheast Feb 2020
Solar + storage project IC-850, Autauga County
Solar + storage
88.0 MWWithdrawn / abandoned Autauga, ALSoutheast Feb 2020
Solar + storage project IC-851, Russell County
Solar + storage
88.0 MWWithdrawn / abandoned Russell, ALSoutheast Feb 2020
Gas project IC-147, Walker County
Gas
85.0 MWWithdrawn / abandoned Walker, ALSoutheast Sep 2003
Solar project IC-571, Russell County
Solar
81.8 MWWithdrawn / abandoned Russell, ALSoutheast Dec 2016
Onshore wind project IC-287, Etowah County
Onshore wind
80.5 MWWithdrawn / abandoned Etowah, ALSoutheast Mar 2013
Solar + storage project IC-1093, Lowndes County
Solar + storage
80.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Nov 2022
Solar + storage project IC-915, Autauga County
Solar + storage
80.0 MWWithdrawn / abandoned Autauga, ALSoutheast Nov 2020target 2024
Solar + storage project IC-785, Calhoun County
Solar + storage
80.0 MWWithdrawn / abandoned Calhoun, ALSoutheast Mar 2019
Solar project IC-914, Autauga County
Solar
80.0 MWWithdrawn / abandoned Autauga, ALSoutheast Nov 2020
Solar project IC-427, Montgomery County
Solar
80.0 MWWithdrawn / abandoned Montgomery, ALSoutheast Jan 2016
Solar project IC-983, Mobile County
Solar
80.0 MWWithdrawn / abandoned Mobile, ALSoutheast Sep 2021target 2027
Solar + storage project IC-913, Autauga County
Solar + storage
80.0 MWWithdrawn / abandoned Autauga, ALSoutheast Nov 2020
Solar + storage project IC-998, Baldwin County
Solar + storage
80.0 MWWithdrawn / abandoned Baldwin, ALSoutheast Dec 2021target 2026

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)