GAS Β· SOUTHEAST

Gas project IC-147, Walker County

Gas project IC-147, Walker County is a 85.0 MW gas request withdrawn in the Southeast interconnection queue, in Walker County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2003 (completed)
  2. Withdrawn / abandonedDec 2003 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-147
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Jasper - Lay Dam 161 kV
Location
Walker County, Alabama
Technology
Gas: 85.0 MW
Total requested
85.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
21 September 2003
Withdrawn
December 2003

Location

Marker shows the centre of Walker County; the queue data does not give exact sites.