United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in PJM (Mid-Atlantic, Midwest) (2019 requests) β page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Ontelaunee Power Generating Plant Battery storage |
20.0 MW | Agreement signed |
| Dover Solar Solar |
20.0 MW | Paused / redesign |
| HU-Logging Solar |
20.0 MW | Paused / redesign |
| Charles County Solar I Solar |
20.0 MW | Paused / redesign |
| SunEast Hooversville Solar Solar |
20.0 MW | Paused / redesign |
| Knoxville Solar Solar |
20.0 MW | Agreement signed |
| Knoxville Solar Solar |
20.0 MW | Agreement signed |
| Harrowgate 1 Solar |
20.0 MW | Agreement signed |
| SunEast Hooversville Solar Solar |
20.0 MW | Paused / redesign |
| Middle Battery Storage Battery storage |
20.0 MW | Agreement signed |
| Limestone Solar Solar |
20.0 MW | Agreement signed |
| UN-Kylertown Solar |
20.0 MW | Agreement signed |
| Limestone Solar Solar |
20.0 MW | Agreement signed |
| Jackson Center Solar II Solar |
20.0 MW | Agreement signed |
| Charles County Solar II Solar |
20.0 MW | Paused / redesign |
| Jakes Hollow Solar Solar |
20.0 MW | Paused / redesign |
| Mansfield #3 Battery storage |
20.0 MW | Agreement signed |
| Houses Corner Storage Battery storage |
20.0 MW | Agreement signed |
| Walnut Solar I Solar |
19.9 MW | Agreement signed |
| Angelina Solar I Solar |
18.0 MW | Agreement signed |
| Welcome Solar III, LLC Solar + storage |
17.9 MW | Agreement signed |
| G Morris Solar Solar |
17.0 MW | Paused / redesign |
| Concho Solar I Solar |
17.0 MW | Paused / redesign |
| BL-Diamond Bear Rocks Solar |
16.3 MW | Agreement signed |
| Ce-Filmore Solar |
16.0 MW | Paused / redesign |
| Shands Energy Center Battery storage |
15.7 MW | Agreement signed |
| FU-Hanks Solar Solar |
15.7 MW | Paused / redesign |
| Jarratt Solar Solar |
14.9 MW | Agreement signed |
| Solar project AF2-039, Clearfield County Solar |
13.5 MW | Agreement signed |
| CL-Route 58 B Solar |
13.5 MW | Paused / redesign |
| SunEast Hooversville Solar Solar |
10.0 MW | Paused / redesign |
| West Lorain 138 kV Power Plant Gas |
8.0 MW | Agreement signed |
| Maryland Offshore Wind Energy Project (MOWEP) Offshore wind |
7.3 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)36 Β· 21.8 GW
- West (non-ISO utilities)72 Β· 21.7 GW
- MISO (Midcontinent)130 Β· 20.0 GW
- PJM (Mid-Atlantic, Midwest)183 Β· 19.2 GW
- ERCOT (Texas)72 Β· 13.4 GW
- Southeast (non-ISO utilities)37 Β· 6,006 MW
- SPP (Southwest Power Pool)21 Β· 2,722 MW
- NYISO (New York)31 Β· 2,705 MW
- ISO-NE (New England)7 Β· 1,764 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)