United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2019 requests) β€” page 30

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests Β· page 30 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 25592, Lee County
Solar
2.0 MWWithdrawn / abandoned Lee, SCSoutheast Jan 2019
Solar project AE2-098, Warren County
Solar
1.9 MWWithdrawn / abandoned Warren, NJPJM Feb 2019target 2020
SHIELD Solar
Solar Β· MERIT SI DEVELOPMENT, LLC
1.9 MWWithdrawn / abandoned Crane, TXERCOT Jun 2019target 2023
Hydro project TCS-49, Fremont County
Hydro
1.8 MWWithdrawn / abandoned Fremont, IDWest Oct 2019
Hydro project 1182, Fremont County
Hydro
1.8 MWWithdrawn / abandoned Fremont, IDWest Oct 2019
Hydro project 1158, Douglas County
Hydro
1.8 MWWithdrawn / abandoned Douglas, ORWest Sep 2019target 2022
Solar project AE2-083, Mercer County
Solar
1.6 MWWithdrawn / abandoned Mercer, NJPJM Feb 2019target 2020
Solar project AE2-164, Bergen County
Solar
1.4 MWWithdrawn / abandoned Bergen, NJPJM Mar 2019target 2020
Solar project TCS-35, Box Elder County
Solar
1.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Willow Brook Road Solar II
Solar
1.0 MWWithdrawn / abandoned Monmouth, NJPJM Jan 2019target 2022
Battery storage project AE2-063, Will County
Battery storage
1.0 MWWithdrawn / abandoned Will, ILPJM Feb 2019target 2019
Solar project AE2-163, Essex County
Solar
1.0 MWWithdrawn / abandoned Essex, NJPJM Mar 2019target 2020
Solar project 1145, Box Elder County
Solar
1.0 MWWithdrawn / abandoned Box Elder, UTWest Jun 2019target 2021
Solar project 1152, Utah County
Solar
0.7 MWWithdrawn / abandoned Utah, UTWest Jul 2019
Solar project 1150, Benton County
Solar
0.5 MWWithdrawn / abandoned Benton, ORWest Jul 2019
Solar project 1124, Deschutes County
Solar
0.4 MWWithdrawn / abandoned Deschutes, ORWest Apr 2019target 2019
Solar project 1128, Jefferson County
Solar
0.4 MWWithdrawn / abandoned Jefferson, ORWest Apr 2019target 2019
Solar project 1125, Deschutes County
Solar
0.4 MWWithdrawn / abandoned Deschutes, ORWest Apr 2019target 2019
Solar project 1121, Wallowa County
Solar
0.4 MWWithdrawn / abandoned Wallowa, ORWest Mar 2019target 2019
Solar project 1187, Grand County
Solar
0.3 MWWithdrawn / abandoned Grand, UTWest Oct 2019target 2020
Solar project 1151, Benton County
Solar
0.3 MWWithdrawn / abandoned Benton, ORWest Jul 2019
Solar project 1149, Benton County
Solar
0.1 MWWithdrawn / abandoned Benton, ORWest Jul 2019
Snyder Wind Repower
Onshore wind
-15.0 MWWithdrawn / abandoned Scurry, TXERCOT Mar 2019
Page 30 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)