United States › Grid › Interconnection queues › Arkansas

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Arkansas — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13431.7 GW
Active in queue35.4 GW157 requests
Agreement signed1,783 MW13 requests
Withdrawn32457.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

134 requests · page 3 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2818, Ouachita County
Solar + storage
130 MWIn study Ouachita, ARMISO Oct 2025target 2025
Solar project J2881, Jefferson County
Solar
125 MWIn study Jefferson, ARMISO Sep 2022target 2026
Solar + storage project J3109, Lonoke County
Solar + storage
120 MWIn study Lonoke, ARMISO Sep 2022target 2026
Solar project J2350, Pulaski County
Solar
116 MWIn study Pulaski, ARMISO Sep 2022target 2025
Solar + storage project J4139, Nevada County
Solar + storage
115 MWIn study Nevada, ARMISO Sep 2025target 2030
Solar project J2639, Bradley County
Solar
106 MWIn study Bradley, ARMISO Sep 2022target 2025
Solar project J2634, Ouachita County
Solar
106 MWIn study Ouachita, ARMISO Sep 2022target 2025
Solar project J3081, Hot Spring County
Solar
105 MWIn study Hot Spring, ARMISO Jul 2025target 2026
Gas project GEN-2024-003, Franklin County
Gas
102 MWIn study Franklin, ARSPP Apr 20242025
Solar + storage project J2773, Poinsett County
Solar + storage
100 MWIn study Poinsett, ARMISO Sep 2022target 2027
Solar project J2954, Clay County
Solar
100 MWIn study Clay, ARMISO Sep 2022target 2026
Solar project J3917, Columbia County
Solar
100 MWIn study Columbia, ARMISO Nov 2024target 2029
Solar project J1820, Lee County
Solar
100 MWIn study Lee, ARMISO Jun 2020target 2026
Solar + storage project J3111, Craighead County
Solar + storage
100 MWIn study Craighead, ARMISO Sep 2022target 2026
Solar + storage project J3112, Phillips County
Solar + storage
100 MWIn study Phillips, ARMISO Sep 2022target 2026
Solar project J3035, Desha County
Solar
100 MWIn study Desha, ARMISO Sep 2022target 2026
Solar + storage project J2133, White County
Solar + storage
100 MWIn study White, ARMISO Aug 2021target 2024
Solar project J1577, Grant County
Solar
100 MWIn study Grant, ARMISO Jun 2020target 2025
Solar project J3141, Phillips County
Solar
100 MWIn study Phillips, ARMISO Sep 2022target 2026
Solar project J3481, Grant County
Solar
100 MWIn study Grant, ARMISO Apr 2024target 2027
Solar project J1612, Union County
Solar
100 MWIn study Union, ARMISO Jun 2020target 2024
Solar + storage project J2456, Phillips County
Solar + storage
100 MWIn study Phillips, ARMISO Sep 2022target 2027
Solar project J2742, White County
Solar
100 MWIn study White, ARMISO Sep 2022target 2026
Solar project J3953, Faulkner County
Solar
90.0 MWIn study Faulkner, ARMISO Nov 2024target 2028
Solar + storage project J4029, Mississippi County
Solar + storage
85.0 MWIn study Mississippi, ARMISO Jun 2025target 2025
Solar + storage project J4038, St. Francis County
Solar + storage
80.0 MWIn study St. Francis, ARMISO Jun 2025target 2030
Solar project J2986, Arkansas County
Solar
80.0 MWIn study Arkansas, ARMISO Sep 2022target 2025
Solar project J2010, Arkansas County
Solar
75.0 MWIn study Arkansas, ARMISO Aug 2021target 2028
Solar + storage project J2871, Mississippi County
Solar + storage
70.0 MWIn study Mississippi, ARMISO Oct 2025target 2025
Battery storage project GEN-2024-243, Crawford County
Battery storage
50.1 MWIn study Crawford, ARSPP Mar 2025target 2029
Battery storage project GEN-2023-206, Sebastian County
Battery storage
50.0 MWIn study Sebastian, ARSPP Oct 2023target 2029
Solar project J1670, Mississippi County
Solar
50.0 MWIn study Mississippi, ARMISO Jun 2020target 2025
Solar project GEN-2024-312, Franklin County
Solar
50.0 MWIn study Franklin, ARSPP Mar 2025target 2030
Coal project J2081, Mississippi County
Coal
20.0 MWIn study Mississippi, ARMISO Aug 2021target 2027
Page 3 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)