Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown413104.6 GW
Active in queue14.4 GW91 requests
Agreement signed3,122 MW15 requests
Withdrawn413104.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

413 requests · page 3 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project IC-812, Montgomery County
Solar + storage
220 MWWithdrawn / abandoned Montgomery, ALSoutheast Oct 2019
Solar + storage project IC-848, Autauga County
Solar + storage
220 MWWithdrawn / abandoned Autauga, ALSoutheast Feb 2020
Solar project IC-817, Dallas County
Solar
220 MWWithdrawn / abandoned Dallas, ALSoutheast Oct 2019
Solar + storage project IC-818, Houston County
Solar + storage
220 MWWithdrawn / abandoned Houston, ALSoutheast Oct 2019
Solar + storage project IC-895, Hale County
Solar + storage
200 MWWithdrawn / abandoned Hale, ALSoutheast Jul 2020
Solar project 408, Colbert County
Solar
200 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar + storage project IC-879, Baldwin County
Solar + storage
200 MWWithdrawn / abandoned Baldwin, ALSoutheast Jun 2020target 2024
Solar project IC-1164, Mobile County
Solar
200 MWWithdrawn / abandoned Mobile, ALSoutheast Aug 2023target 2027
Battery storage project IC-1175, Etowah County
Battery storage
200 MWWithdrawn / abandoned Etowah, ALSoutheast Sep 2023target 2027
Solar project IC-795, Hale County
Solar
200 MWWithdrawn / abandoned Hale, ALSoutheast May 2019
Solar project IC-874, Fayette County
Solar
200 MWWithdrawn / abandoned Fayette, ALSoutheast May 2020
Solar project 386, Colbert County
Solar
200 MWWithdrawn / abandoned Colbert, ALSoutheast Aug 2019
Solar + storage project IC-1173, Talladega County
Solar + storage
200 MWWithdrawn / abandoned Talladega, ALSoutheast Sep 2023target 2026
Solar project 409, Colbert County
Solar
200 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar + storage project 525, Lawrence County
Solar + storage
200 MWWithdrawn / abandoned Lawrence, ALSoutheast Nov 2022
Solar + storage project 451, Colbert County
Solar + storage
200 MWWithdrawn / abandoned Colbert, ALSoutheast Jul 2020
Solar + storage project 521, Colbert County
Solar + storage
200 MWWithdrawn / abandoned Colbert, ALSoutheast Sep 2022target 2026
Solar project 324, Limestone County
Solar
200 MWWithdrawn / abandoned Limestone, ALSoutheast Aug 2017
Solar project IC-875, Randolph County
Solar
200 MWWithdrawn / abandoned Randolph, ALSoutheast May 2020target 2024
Solar + storage project IC-880, Baldwin County
Solar + storage
200 MWWithdrawn / abandoned Baldwin, ALSoutheast Jun 2020target 2024
Battery storage project 670, Jackson County
Battery storage
200 MWWithdrawn / abandoned Jackson, ALSoutheast Oct 2024
Solar + storage project IC-1169, Lowndes County
Solar + storage
200 MWWithdrawn / abandoned Lowndes, ALSoutheast Aug 2023target 2027
Other project 73, Colbert County
Other
200 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 1999
Solar project IC-1212, Perry County
Solar
199 MWWithdrawn / abandoned Perry, ALSoutheast Dec 2023
Solar project 25-IC-1378, Sumter County
Solar
199 MWWithdrawn / abandoned Sumter, ALSoutheast Apr 2025
Solar project 25-IC-AA, Mobile County
Solar
199 MWWithdrawn / abandoned Mobile, ALSoutheast
Solar project 25-IC-AW, Washington County
Solar
199 MWWithdrawn / abandoned Washington, ALSoutheast
Solar project 563, Franklin County
Solar
198 MWWithdrawn / abandoned Franklin, ALSoutheast Jun 2023
Solar project 25-IC-1367, Macon County
Solar
195 MWWithdrawn / abandoned Macon, ALSoutheast Apr 2025
Solar project 25-IC-1362, Marengo County
Solar
195 MWWithdrawn / abandoned Marengo, ALSoutheast Apr 2025
Solar + storage project 25-IC-1351, Barbour County
Solar + storage
190 MWWithdrawn / abandoned Barbour, ALSoutheast Apr 2025
Solar project IC-1273, Clarke County
Solar
180 MWWithdrawn / abandoned Clarke, ALSoutheast Mar 2024
Solar project 480, Colbert County
Solar
170 MWWithdrawn / abandoned Colbert, ALSoutheast Aug 2021
Solar + storage project 498, Colbert County
Solar + storage
170 MWWithdrawn / abandoned Colbert, ALSoutheast Apr 2022target 2027
Solar project IC-1178, Baldwin County
Solar
160 MWWithdrawn / abandoned Baldwin, ALSoutheast Sep 2023target 2030
Solar project 25-IC-1345, Baldwin County
Solar
160 MWWithdrawn / abandoned Baldwin, ALSoutheast Apr 2025
Solar project IC-984, Mobile County
Solar
160 MWWithdrawn / abandoned Mobile, ALSoutheast Sep 2021
Solar project 25-IC-1381, Sumter County
Solar
156 MWWithdrawn / abandoned Sumter, ALSoutheast Apr 2025
Solar project 410, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast Nov 2019
Solar + storage project 516, Lauderdale County
Solar + storage
150 MWWithdrawn / abandoned Lauderdale, ALSoutheast Aug 2022target 2024
Solar project 25-IC-BA, Shelby County
Solar
150 MWWithdrawn / abandoned Shelby, ALSoutheast
Solar project IC-1277, Escambia County
Solar
150 MWWithdrawn / abandoned Escambia, ALSoutheast Apr 2024
Solar + storage project IC-856, Houston County
Solar + storage
150 MWWithdrawn / abandoned Houston, ALSoutheast Feb 2020
Solar project IC-317, Lowndes County
Solar
150 MWWithdrawn / abandoned Lowndes, ALSoutheast Oct 2013
Solar project IC-1118, Houston County
Solar
150 MWWithdrawn / abandoned Houston, ALSoutheast Feb 2023
Solar project 667, Lawrence County
Solar
150 MWWithdrawn / abandoned Lawrence, ALSoutheast Oct 2024
Solar project 576, Colbert County
Solar
150 MWWithdrawn / abandoned Colbert, ALSoutheast Jul 2023target 2025
Solar project 302, Jackson County
Solar
150 MWWithdrawn / abandoned Jackson, ALSoutheast Sep 2016
Solar project IC-767, Shelby County
Solar
150 MWWithdrawn / abandoned Shelby, ALSoutheast Dec 2018target 2022
Solar project 347, Lawrence County
Solar
150 MWWithdrawn / abandoned Lawrence, ALSoutheast Apr 2018

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20102025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)