Requests shown32584.1 GW
Active in queue84.1 GW325 requests
Agreement signed0.1 MW1 requests
Withdrawn7520.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

325 requests Β· page 3 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project S0035, Washington County
Gas
300 MWIn study Washington, UTWest Apr 2025target 2027
Solar project GI-CS-2025-05, Weld County
Solar
300 MWIn study Weld, COWest Sep 2025target 2029
Battery storage project T2-075, San Juan County
Battery storage
300 MWIn study San Juan, UTWest Sep 2025target 2027
Solar project 25-00381, Lassen County
Solar
300 MWIn study Lassen, CAWest Jul 2025target 2029
Solar + storage project GI-2025-02, Cheyenne County
Solar + storage
300 MWIn study Cheyenne, COWest Apr 2025target 2030
Other project Q597, Yuma County
Other
300 MWIn study Yuma, AZWest May 2025target 2029
Onshore wind project T2-025, Bingham County
Onshore wind
300 MWIn study Bingham, IDWest Sep 2025target 2030
Other project GI-CS-2025-29, Yuma County
Other
300 MWIn study Yuma, COWest Oct 2025target 2031
Other project Q586, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2030
Solar + storage project GI-2025-01, Morgan County
Solar + storage
300 MWIn study Morgan, COWest Apr 2025target 2030
Solar + storage project GI-CS-2025-03, Kit Carson County
Solar + storage
300 MWIn study Kit Carson, COWest Sep 2025target 2028
Solar + storage project T2-056, Juab County
Solar + storage
300 MWIn study Juab, UTWest Sep 2025target 2029
Onshore wind project CS25-11, Garfield County
Onshore wind
300 MWIn study Garfield, WAWest Apr 2025target 2029
Solar + storage project T2-028, Iron County
Solar + storage
300 MWIn study Iron, UTWest Sep 2025target 2029
Es300B
Battery storage
300 MWIn study Otero, NMWest Jun 2025target 2028
Gas project T2-059, Utah County
Gas
300 MWIn study Utah, UTWest Sep 2025target 2025
Other project Q578, Pinal County
Other
300 MWIn study Pinal, AZWest Apr 2025target 2029
Other project Q607, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q582, Maricopa County
Other
275 MWIn study Maricopa, AZWest May 2025target 2030
Solar + storage project T2-023, Juab County
Solar + storage
275 MWIn study Juab, UTWest Sep 2025target 2026
Battery storage project Q2510, Maricopa County
Battery storage
264 MWIn study Maricopa, AZWest Feb 2025target 2028
Ca-CO-250B
Battery storage
250 MWIn study El Paso, TXWest Jun 2025target 2029
Other project SC1Q33, Sacramento County
Other
250 MWIn study Sacramento, CAWest Jul 2025target 2030
Other project Q593, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q595, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q594, Pinal County
Other
250 MWIn study Pinal, AZWest May 2025target 2029
Other project Q618, Pima County
Other
250 MWIn study Pima, AZWest May 2025target 2030
Solar + storage project IA-PNM-2025-04, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2028
Battery storage project CS25-08, Spokane County
Battery storage
250 MWIn study Spokane, WAWest Apr 2025target 2029
Battery storage project 25-00431, Storey County
Battery storage
250 MWIn study Storey, NVWest Jul 2025target 2029
Other project Q598, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q610, San Juan County
Other
250 MWIn study San Juan, NMWest May 2025target 2029
Onshore wind project IA-PNM-2025-18, Torrance County
Onshore wind
250 MWIn study Torrance, NMWest Mar 2025target 2028
Solar + storage project 793, Ada County
Solar + storage
250 MWIn study Ada, IDWest Apr 2025target 2029
Solar + storage project IA-PNM-2025-06, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2031
Solar + storage project T2-053, Iron County
Solar + storage
248 MWIn study Iron, UTWest Sep 2025target 2029
Battery storage project T2-061, Salt Lake County
Battery storage
225 MWIn study Salt Lake, UTWest Sep 2025target 2027
Solar + storage project IA-PNM-2025-05, Bernalillo County
Solar + storage
225 MWIn study Bernalillo, NMWest Mar 2025target 2030
Onshore wind project GI-CS-2025-24, Kit Carson County
Onshore wind
225 MWIn study Kit Carson, COWest Sep 2025target 2029
Solar + storage project T2-032, Jefferson County
Solar + storage Β· PacifiCorp
205 MWIn study Jefferson, ORWest Sep 2025target 2028
Battery storage project S0037, Emery County
Battery storage
200 MWIn study Emery, UTWest Jun 2025target 2027
Other project 37681, Platte County
Other
200 MWIn study Platte, WYWest Jul 2025target 2029
Geothermal project 25-00405, Churchill County
Geothermal
200 MWIn study Churchill, NVWest Jul 2025target 2029
Other project 38047, Platte County
Other
200 MWIn study Platte, WYWest Jul 2025target 2029
Battery storage project GI-SISS-2025-06, Logan County
Battery storage
200 MWIn study Logan, COWest Oct 2025target 2027
Other project Q585, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2030
Battery storage project GI-RSC-2025-02, Moffat County
Battery storage
200 MWIn study Moffat, COWest Jul 2025target 2029
Battery storage project GI-SISS-2025-03, Mckinley County
Battery storage
200 MWIn study Mckinley, NMWest Jul 2025target 2027
Other project Q605, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2031
Onshore wind project CS25-15, Spokane County
Onshore wind
200 MWIn study Spokane, WAWest Apr 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)